THE MINISTER OF POWER ( SHRI SURESH PRABHU )
(a) to (d) : A Statement is laid on the Table of the House.
STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (d)
OF STARRED QUESTION NO. 536 TO BE ANSWERED IN THE
LOK SABHA ON 02.05.2002 REGARDING POWER PROJECTS
BY THE MULTINATIONAL COMPANIES.
(a) to (d) : Government of India (GOI) announced a power policy in 1991
aimed at encouraging the flow of private capital of the power sector. This
policy applies equally to all the States and regions including backward areas.
The location of a power project in a State is determined keeping in view
certain essential techno-economic details such as distance from source of
fuel, transportation of fuel, water availability, feasibility of establishing the
project from environmental and forest aspects, feasibility of power
evacuation to the load center, etc. Since the inception of the private power
policy and till date, Central Electricity Authority (CEA) has accorded techno-
economic clearance to 58 projects, including those from multinational
companies, having an aggregate capacity of 29614.5 MW for which complete
Detailed Project Reports (DPRs) had been received. The State-wise details
of these 58 projects, indicating their promoters, location and commissioning
schedule are given in Annexure.
ANNEXURE REFERRED TO IN PARTS (a) TO (d) OF THE STATEMENT LAID IN REPLY TO STARRED QUESTION NO.536 TO BE ANSWERED IN THE LOK SABHA ON 02.05.2002 REGARDING POWER PROJECTS BY THE MULTINATIONAL COMPANIES.
S.N NAME OF THE PROJECT/ PROJECT CAP(MW) Commissioning schedule PROMOTERS/LOCATION
Himachal Pradesh
1 Baspa Stage - II HEP (M/s JPIL), Kinnaur 300 Expected by July 2002
2 Malana HEP(M/s Rajasthan Spinning & Weaving Mills Ltd), Kullu 86 Commissioned in July, 2001.
3. Dhamwari Sunda HEP, Shimla 70 Expected by Oct 2006
Uttar Pradesh
4 Vishnuprayag HEP (M/s JPIL), Chamoli 400 60 months from financial closure
5 Rosa TPP (M/s. Indo-Gulf Fertilizers), Shahjhanpur 567 40 months from financial closure
6 Srinagar HEP (M/s Duncans North Hydro Power Co. Ltd.), Pauri Garhwal 330 62 months from financial closure
Rajasthan
7 Dholpur CCGT (M/s RPG Dholpur Power Co.Ltd.),Dholpur 702.7 24- 28 months from financial closure
8+ Barsingsar TPP( M/s Hindustan Vidyut Corporation Ltd.), Bikaner 500 38-42 months from financial closure
Chhattisgarh
9 Korba(East)TPP (M/s Daewoo Power), Bilaspur 1070 41- 47 months from financial closure.
10 Korba (West) Extn. (M/s ITPL), Bilaspur 420 33-36 months from financial closure
11 Bhilai TPP (M/s Bhilai Power Supply Comp.), Durg. 574 39 months from financial closure
12 Raigarh TPP(M/s Jindal Power Ltd.), Raigarh 550 36-39 months from financial closure
Madhya Pradesh
13 Maheshwar HEP(M/s. S. Kumars Ltd.), Khargone 400 55- 56 months from financial closure.
14 Bina TPP (M/s. Bina Power Supply Co. Ltd.), Sagar 578 33-36 months from financial closure
15 Narsinghpur CCPP(M/s GBL Power ), Narsinghpur 166 23 months from financial closure
16 Guna CCGT (M/s. STI Power India Ltd.), Guna 330 12-25 months from financial closure
17 Pench TPP (M/s. Pench Power Ltd.), Chindawara 500 38-41 months from financial closure
18 Bhander CCGT (M/s Bhander Power Ltd.), Gwalior. 342 12-25 months from financial closure
19 Pithampur DGPP (M/s Shapoorji Pallonji Power Co. Ltd.), Dhar 119.7 14-17 months from financial closure
20 Ratlam DGPP (M/s GVK Power (Ratlam) Ltd.), Ratlam. 118.63 14-17 months from financial closure
21 Khandwa CCGT (M/s Madhya Bharat Energy Corp. Ltd.), East Nimar 171.17 22 months from financial closure
Gujarat
22 Paguthan CCGT ( M/s Gujarat Torrent ), Bharuch 654.7 Commissioned in 1998/1999
23 Hazira CCGT (M/s. Essar Power Ltd.), Surat. 515.0 Commissioned in 1997
24 Baroda CCGT (M/s. GIPCL), Baroda 167.0 Commissioned during 1997
25 Surat Lignite TPP (M/s GIPCL), Surat 250.0 Commissioned during 1999
26 Jamnagar TPP (M/s Reliance Power Ltd.), Jamnagar 500.0 36-39 months from financial closure
Maharashtra
27 Dabhol CCGT (M/s. Dabhol Power Co.), Ratnagiri 2015 Stage-I Commissioned in 1999 Stage-II was expected in 2001-2002. Construction work has been suspended by the contractor.
28 Bhadravati TPS (M/s. Central India Power), Chandrapur. 1072 42-48 months from Financial Closure
29 Patalganga CCGT (M/s Reliance Patalganga Power ), Raigarh 447.1 18-24 months from Financial Closure
Andhra Pradesh
30 Jegurupadu CCGT (M/s. GVK Industries), East Godavari 216 Commissioned in 1997
31 Godavari CCGT (M/s. Specturam Tech.) East Godavari 208 Commissioned in 1998
32 Vizag TPS (M/s.HNPCL),Vishakhapattanam 1040 38-44 months from Financial Closure
33 Ramagundam Extn.( M/s BPL Group), Karimnagar 520 33-39 months from Financial Closure
34 Kondapally CCGT(Lanco Industries Ltd.), Krishna 350 Commissioned during June-October, 2000.
35. Krishnapatnam âBâ TPP (BBI Power Krishnapatnam Co.), Nellore 520 36-42 months from Financial Closure
36. Vemagiri CCGT (Ispat Power Limited), East Godavari 492 20-26 months from Financial Closure
Karnataka
37 Toranagallu TPS (M/s. Jindal Tractebel ) , Bellari 260 Commissioned in 1999
38 Mangalore TPS (M/s. Cogentrix), South Canara 1013.2 33 months from Financial Closure
39 Nagarjuna TPP (M/s Nagarjuna Power Corporation Ltd.), Udupi 1015 38-42 months from Financial Closure
40 Bangalore CCPP (M/s. Peenya Power), Bangalore 107.6 19 months from Financial Closure
Tamil Nadu
41 Neyveli TPS - Zero Unit (Ms. ST-CMS), South Arcot 250 34 months from financial closure
42 Pillaiperumalnallur CCGT(M/s PPN Power), Thanjavur 330.5 Commissioned in 2000-2001
43 North Madras TPS -II(M/s. Videocon Power), Tiruvallur 1050 42-46 months from Financial Closure
44 Basin Bridge DGPP (M/s. GMR Vasavi ), Madras 200 Commissioned in 1998-1999
45 Tuticorin TPP St. IV (M/s. SPIC ), Chidambarnar 525 39 months from Financial Closure
46 Samayanallur DGPP (M/s Balaji Power Corp. Ltd.), Madurai 106 Commissioned in Oct., 2001
47 Samalpatti DGPP(M/s Samalpatti Power Co.), Dharampur 106 Commissioned in March, 2001.
48 North Madras TPP( M/s Tri-Sakthi Energy Private Limited), Tiruvallur 525 37 months from Financial Closure
49 Cuddalore TPP (M/s Cuddalore Power Company), South Arcot 1320 39-44 months from Financial Closure
50 Vembar CCGT (M/s Indian Power Projects Limited), Ramanathapuram 1873 38-50 months from Financial Closure
Kerala
51 Vypeen CCGT(M/s Siasin Energy Pvt. Ltd.), Ernakulam 679.2 27 months from Financial Closure
52. Kannur CCGT (M/s Kannur Power Projects Ltd.), Kannur 513 27 months from Financial Closure
Orissa
53 Ib Valley TPS (Units 5 &6) (AES IB Valley Cor.), Jharsuguda 500 33-36 months from Financial Closure
54 Duburi TPP Units 1 & 2 ( Kalinga Power Corporation), Jajpur 500 33-36 months from Financial Closure
West Bengal
55 Balagarh TPS (M/s. Balagarh Power Com.), Hoogli 500 33-36 months from Financial Closure
56+ Bakreshwar TPP ( Bakreshwar Power Gen. Co. Ltd) , Birbhum 420 30-33 months from Financial Closure
57+ Gouripore TPP (Gouripore Power Company), North 24 Parganas 150 32 months from Financial Closure
Bihar
58 Jojobera TPP (M/s Jamshedpur Power Co), Jamshedpur 240 1st Unit commissioned in October, 2000 2nd Unit commissioned in August, 2001.
+ Projects are no longer being pursued by the respective State Governments in the private sector.