Question : Bareilly-Sitapur National Highway

(a) the present status of construction of Bareilly-Sitapur National Highway-30 in Uttar Pradesh;
(b) the funds spent thereon so far;
(c) the time by which construction of this road is likely to be completed; and
(d) whether the materials are being used as per prescribed standards in construction of this road and if not, the steps being taken by the Government in this regard?

Answer given by the minister

THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS

(SHRI NITIN JAIRAM GADKARI)

(a) to (c) The construction of balance work of Bareilly-Sitapur section has already commenced on 17.12.2019. As on date, the expenditure on this project is Rs. 403 crore. The work is scheduled to be completed in March 2021.
(d) The material which is being used for construction of this road is as per the technical specifications.

*****