Question : SONIA VIHAR WATER TREATMENT PLANT



(a) whether delay in completion of Water Treatment Plant at Sonia Vihar, Delhi by 16 months has led to its cost escalation by crores of rupees;

(b) if so, the reasons therefor;

(c) whether the Government is not able to provide water for the said plant which was completed six months ago; and

(d) if so, the details thereof alongwith loss being suffered by the Government on the account of penalty to French firm?

Answer given by the minister


MINISTER OF PARLIAMENTARY AFFAIRS AND URBAN DEVELOPMENT( SHRI GHULAM NABI AZAD )

(a)&(b): The Delhi Jal Board (DJB) has informed that work on Sonia Vihar Water Treatment Plant was to be completed by 4th June, 2004. However, no cost escalation claim on account of delay has been received from the Contractor.

(c)&(d): The raw water for the plant has not been made available by the Government of Uttar Pradesh from Tehri Dam Storage. However, no penalty is payable by the Government/DJB. The contract provides for payment of some specified charges if raw water is not made available after the plant becomes operational. No such specific charge have been paid by DJB so far.