THE MINISTER OF STATE IN THE MINISTRY OF POWER (SHRI BHARATSINH SOLANKI)
(a) & (b): A total of 36 nos. of thermal units (4791 MW) for life extension (LE),
61 nos. of thermal units (15075 MW) for renovation & modernization (R&M) and 32 numbers
of hydro stations (10016 MW) have been identified during the last three years. The
details of the identified units and the status of the plants, where work have been
completed and those where works are under progress is enclosed (Annex-I for thermal
and Annex-II for hydro plants respectively).
(c) & (d): Yes, Madam, some difficulties are being encountered in execution of
work mainly:
i. Procedural delay in the formulation of schemes and finalisation of orders by SEBs/Utilities.
ii. Poor response from various agencies to conduct Residual Life Assessment (RLA)/Condition Assessment (CA) studies. Lack of standardization in results of RLA studies.
iii. Delay in finalizing detail project reports (DPRs).
iv. Reluctance on the part of SEBs/Utilities to undertake renovation and modernization since this needs to the units going out of the system temporarily, thereby lowering generation.
v. The response from bidder for R&M works have been poor and in some cases, single bids were received resulting delay in award of works.
vi. Delay in supply of material and execution of R&M/LE works as it is considered as a non-priority activity resulting into non-adherence to completion schedule.
vii. Technical surprises during the time of execution.
(e): The following steps are proposed for timely completion of R&M activities:
(i) The utilities generally prefer to go for direct placement of order for R&M works
to the original equipment manufacturer (OEM). This approach has resulted in accumulated
work orders with the indigenous manufacturers thereby resulting in delay in supplying of
spares / equipment. Now, BHEL the main OEM supplier has taken steps towards augmenting
its manufacturing capacity to cater to R&M works besides meeting the requirement of new
generation projects. In order to make implementation of R&M schemes more broad based
and to ensure the participation of more contracting agencies, the process of competitive
bidding is being encouraged.
(ii) In order to make R&M investment more cost effective and self sustaining, the
option of integrating the objective of plant efficiency improvement with that of R&M
scheme is being proposed where ever it is found techno economically viable. In this
regard the financial assistance through bi-lateral co-operation from Germany, World
Bank, JBIC etc. are also being envisaged besides fund availability from Indian
agencies such as PFC & REC.