Question : IRRIGATION PROJECTS OF ORISSA



(a) whether target dates were fixed for completion of irrigation projects in Orissa during the Ninth Five Year Plan;

(b) if so, the names and the number of projects;

(c) whether any of these projects have been completed as per schedule;

(d) if not, the reasons therefor; and

(e) the time by when the projects are likely to be completed?

Answer given by the minister


THE MINISTER OF WATER RESOURCES (SHRI ARJUN CHARAN SETHI)

(a) to (e) The details of ongoing major/medium irrigation projects of Orissa identified by the Ministry of Water Resources for completion during IX plan are given in the statement enclosed. The main reasons for delay in completion of these irrigation projects are paucity of funds and delay in land acquisition.

STATMENT REFERRED TO IN REPLY TO PARTS (a) TO (e) OF LOK SABHA UNSTARRED QUESTION NO.3680 FOR ANSWER ON 07.04.2003 REGARDING IRRIGATION PROJECTS OF ORISSA.

Ongoing Major and Medium Projects of Orissa identified by Ministry of Water Resources for completion during IX Plan

(Amount Rs. in crore)/ (Potential in Th. Ha.)
Sl Project Start Estimated Cost Cumulative Ultimate Potent Completi District Name ed in Expenditur Potential ial on Date Benefitt No Plan e upto end create ed of IX Plan d upto IX Plan Original Latest Amount
Major Projects
1 Potteru IV 14.81 162.86 174.37 109.88 102.62 # Malkangiri 2 Upper Kolab V 24.05 492.32 298.24 88.76 84.44 2003 Koraput
Medium Project
1 Baghua St.I AP 0.83 91.75 1.35 4.05 - # Ganjam 78-80 2 Badnala VII 15.36 105.88 121.10 13.74 11.00 # Koraput 3 Birupa VII 4.03 11.46 12.99 6.92 4.09 # Cuttak Genguti Island Irrigation
4 Sapuabadajore VI 14.87 59.03 22.11 3.75 5.10 # Dankanal 5 Satiguda VII - 4.52 1.77 13.59 12.02 # Malkangiri

# Projects yet to be completed