THE MINISTER OF STATE IN THE MINISTRY OF ROAD TRANSPORT AND HIGHWAYS
(SHRI R. P. N. SINGH)
(a) & (b) : Yes Sir. A length of about 96 km of National Highway No.80 is single lane
out of total length of 296.26 km. This includes 20 km length in Bihar, 63 km in Jharkhand and
13 km in West Bengal.
(c) to (e) : 70 Km length of NH-80 in Bihar is included under the National Highway
Development Project (NHDP) Phase-III. The development of balance length of NH-80 in Bihar,
Jharkhand and West Bengal is taken up through budgetary resources in a phased manner based on
the need of traffic, inter-se priority and availability of funds. 12 nos. of works amounting
to Rs.79.90 crore have been sanctioned for improvement of NH-80 in Bihar. In Jharkhand 4 nos.
of works amounting to Rs.19.83 crore for widening/Improvement of Riding Quality (IRQP) have
been sanctioned during 2008-2009 which are in progress/tender stage. 2 nos. of works for
widening to 2-lane and strengthening for a total length of 28.00 km amounting to Rs.34.00 crore
have been included in the Annual Plan 2009-10. In addition to above provisions for
feasibility study and detailed project report for widening to 2-lane with geometric
improvements for 42 km length and land acquisition for widening from km 210.50 to 213.00
of NH-80 in Jharkhand have been made in the Annual Plan 2009-10. The feasibility study for
development of NH-80 in West Bengal is in progress.