THE MINISTER OF POWER( SHRI P.M. SAYEED )
(a) to (e) : An agreement was reached between the States of Punjab, Haryana and
Rajasthan and Government of India on 10.05.1984 wherein it was agreed that in view of
the claims raised by Haryana & Rajasthan to sharing of power in Anandpur Sahib Hydel
Project, Mukerian Hydel Project, Thein Dam Project, UBDC Stage-II and Shahpur Kandi
Hydel Scheme, the Government of India shall refer the matter to Supreme Court for its
opinion. A reference was to be made to the Supreme Court seeking its opinion whether
the States of Haryana and Rajasthan are entitled to a share in the power generated from
the above mentioned schemes and in case they are, what would be the share of each State.
It was agreed that the Supreme Court`s opinion obtained by Government of India shall be
remitted to the signatory states and shall be binding on them.
The matter has not been referred to Supreme Court. However, a number
of formal and informal discussions have taken place since 1984 to settle the issue
amicably. These issues were also discussed in the Northern Zonal Council meetings held
in 1997 & 1999. Subsequently, numerous discussions have been held with the State
Governments with a view to bring about a consensus on the issues.