Question : Achievements of CIAL

(a) the achievements of Cochin International Airport Limited (CIAL) in generation of solar energy
(b) whether the Government proposes to promote solar energy generation in other airports in the country; and
(c) if so, the details thereof?

Answer given by the minister

THE MINISTER OF STATE FOR POWER, COAL, NEW & RENEWABLE ENERGY AND MINES (INDEPENDENT CHARGE) (SHRI PIYUSH GOYAL)

(a): An aggregate capacity of 21.5 MW solar power plants have been installed at Cochin International Airport Limited (CIAL).
(b) & (c): Yes Madam, An aggregate capacity of 46.693 MW solar power plants have been installed at different airports in the country. The details are given in Annexure.
*********

Download PDF Files