Question : CAPACITY ADDITION OF POWER GENERATION



(a) the details of target for capacity addition of power generation in the Central, State and Private Sectors during the Ninth Plan period;

(b) the details of achievements made during the first three years of the Ninth Plan period;

(c) whether the target in the capacity addition programme is not likely to be achieved;

(d) if so, the reasons therefor; and

(e) the steps proposed by the Government to streamline the programme during the last two years of the plan period?

Answer given by the minister

THE MINISTER OF STATE IN THE MINISTRY OF POWER

( SHRIMATI JAYAWANTI MEHTA )

(a) : A target of 40245.2 MW was fixed for the 9th Plan.

The Sector-wise/type-wise details are given below:

(In MW)	Sector	Hydro	Therma	Nuclear	Total 
Central 3455 7574 880 11909 State 5815 4933 10748 Private 550 17038 17588
Total 9820 29545 880 40245
(b) : The details of achievement made during the first three years of the Ninth Plan is as under:
(IN MW)
1997-98 3226 1998-99 4267 1999-2000 4507
(c) & (d) : According to the Mid-term Appraisal carried out in July, 1999, a capacity addition of 28097 MW is likely to be achieved during the Ninth Plan against the original target of 40245 MW. The reasons for shortfall are:

(i) Delayed financial closures of private sector projects due to non-availability of escrow.

(ii) paucity of Funds for public sector projects.

(iii) Delay in land acquisition

(iv) Delay in investment decision

(v) Resettlement and Rehabilitation problems

(vi) Law and order problems

(vii) Contractual problems

(viii) Inter-State disputes in respect of hydro projects

(e) : Close monitoring is being done by Ministry of Power for timely completion of projects through Empowered Committee and Task Forces constituted in the Ministry. For private sector projects, a Crisis Resolution Group has been set up to resolve the `last mile` problems.