THE MINISTER OF STATE IN THE MINISTRY OF POWER
( SHRIMATI JAYAWANTI MEHTA )
(a) : A target of 40245.2 MW was fixed for the 9th Plan.
The Sector-wise/type-wise details are given below:
(In MW) Sector Hydro Therma Nuclear Total
Central 3455 7574 880 11909 State 5815 4933 10748 Private 550 17038 17588
Total 9820 29545 880 40245
(b) : The details of achievement made during the first
three years of the Ninth Plan is as under:
(IN MW)
1997-98 3226 1998-99 4267 1999-2000 4507
(c) & (d) : According to the Mid-term Appraisal carried out in
July, 1999, a capacity addition of 28097 MW is likely to be
achieved during the Ninth Plan against the original target of
40245 MW. The reasons for shortfall are:
(i) Delayed financial closures of private sector projects
due to non-availability of escrow.
(ii) paucity of Funds for public sector projects.
(iii) Delay in land acquisition
(iv) Delay in investment decision
(v) Resettlement and Rehabilitation problems
(vi) Law and order problems
(vii) Contractual problems
(viii) Inter-State disputes in respect of hydro projects
(e) : Close monitoring is being done by Ministry of
Power for timely completion of projects through Empowered
Committee and Task Forces constituted in the Ministry. For
private sector projects, a Crisis Resolution Group has been set
up to resolve the `last mile` problems.