MINISTER OF STATE IN THE MINISTRY OF SHIPPING
(SHRI PON. RADHAKRISHNAN)
(a)to(c): State-wise present status of various Port Development projects for last three years is given at Annexure-I.
(d) Expansion and upgradation work have been carried out in all Major Ports including those in the State of Tamil Nadu.
(e) Annual target for implementation of port development projects is fixed and the progress is reviewed periodically. Due to close monitoring, targets fixed were achieved successfully during the last three years.
(f) Yes, Madam. Government of India has received a proposal from Government of Kerala for seeking financial support for the upgradation of Azhikkal Port with the project cost of Rs.496 crore. The proposal has been technically appraised by the Ministry of Shipping and Government of Kerala was requested to furnish some additional information alongwith revised Detailed Project Report (DPR) for further consideration. Response from Government of Kerala has not been received.
ANNEXURE
Status of projects awarded in the year 2014 -15
<pre>
State Port Project Cost
(Rs. In crore) Capacity
(In million tonnes Per Annum) Status
Tamil Nadu Chennai Coastal Road Project 63.00 - Completed
Supply, Operation and Maintenance of Harbour Mobile Crane and other Cargo handling equipments 62.57 5.00 Completed
VoC Port Tuticorin Development of road facilities for cargo evacuation from Hare Island (Phase – I) 8.20 6.00
Completed
Capital Dredging Project 440.00 9.00 Completed
Mechanization of cargo evacuation from 9th Berth to Coal yard at the existing Coal Yard 76.25 3.67 Completed
Kamarajar Additional Capital dredging alongside the BOT coal berth(CICTPL) and TNEB Berth & approach channel 53.00 2.00 Completed
Development of rail connectivity to Container terminal & Multi Cargo terminal (total track length – 8.5km) 50.00 4.00 Completed
West Bengal Kolkata Integrated Container handling at Berth 10&11 20.00 1.50 Completed
Grant of licence of M/s. Jindal ITF Ltd. for setting up of Transloading Facilities for handling dry bulk cargo at Haldia Dock Complex. 266.00 6.60 Commissioned
Construction, Operation and maintenance of Fly Ash Handling Jetty at HDC. 2.00 0.75 Completed
Odisha Paradip Development of Clean Multi-cargo Berth in Southern Dock 387.31 5.00 Work in progress. No delay
Development of Deep Draft Iron Ore berth. 740.19 10.00 Work in progress. No delay
Supply, installation of 3 Nos. Of 100 tonne HMC. 117.00 3.00 Completed
Andhra Pradesh Visakhapatnam Northern Arm capital dredging 45.00 10.00 Completed
Kerala Cochin NIL NIL NIL
Karnataka New Mangalore Augmentation of Fire fighting system at Berth No. 13 for Very Large Gas Carriers (VLGC) 35.00
Completed
Goa Mormugao NIL NIL NIL
Maharashtra Mumbai NIL NIL NIL
Jawahar Lal Nehru Earth filling work for Jawaharlal Nehru Port SEZ Phase-I 17.00 -- Completed
Special Economic Zone. 4000.00 6.00 Work in progress. No delay
Construction of ROB in lieu of existing level crossing No. 6 at KM 91/01 and 91/02 ON Panuel- Jasai Lane 55.72 -- Completed
Development of Additional Liquid Terminal 2496.00 26.00 Work in progress. No delay
Development of additional reefer yard 17.00 7.50 Completed
Gujarat Kandla Strengthening of Oil Jetty No. 1 & 2 14.29 1.57 Completed
Up gradation of existing two lane road from NH-8A to Tuna Port 18.26 6.20 Completed
Development of SPM in Oot 448.00 25.00 Work has not been started for want of environment clearance.
Status of projects awarded in the year 2015 -16
<pre>
State Port Project Cost
(Rs. In crore) Capacity
(In million tonnes Per Annum) Status
Tamil Nadu Chennai NIL NIL NIL
VoC Port
Tuticorin Construction of Coastal Berth 90.00 2.50 Work in progress. No delay
Kamarajar Capital Dredging Phase III 425.00 - Work in progress. No delay
Construction of Coal Berth-4 for TANGEDCO 275.00 9.00 Work in progress. No delay
IOC Oil Jetty 600.00 5.00 Work has not been started for want of Environment Clearance.
Dredging to achieve 18m draft for the Port –Phase IV 500.00 9.00 Work has not been started for want of Environment Clearance.
Development of GCB - II 240.00 9.00 Work has not been started for want of Environment Clearance.
West Bengal Kolkata Supply, Operation & Maintenance of cargo handling equipment at berth Nos. 2& 8 of HDC under PPP/allied mode. 110.00 7.00 Completed
Setting up floating Riverine Barge jetty with connecting Road to the storage area 75.00 1.50 Work is in progress. Slight delay due to late receipt of Environment Clearance.
Floating Storage & Regasification Unit (FSRU) 3500.00 4.00 Work not started as SPV has not been constituted.
Mechanisation of Berth No. 13 50.00 2.50 Completed
Odisha Paradip Capital Dredging of BOT dock Basin 174.37
- Work is in progress
LPG Terminal at South Jetty 690.00 0.75 Work has not been started for want of statutory clearance.
Mechanisation of EQ1 to EQ3 berths 1633.44 30.00 Work has not been started. Last date for fulfilling the condition precedent is 28.08.2017 by the concessionaire.
Andhra Pradesh Visakha-patnam Establishment of Container Freight Station through existing BOT operator by VCTPL. 100.00 0.90 Phase-I Completed
Development of Multi Modal Logistic Hub by M/s CONCOR. (Phase-II) 372.00 - Completed.
Installation of two MHC in EQ 5&6 in Inner Harbour 39.00 3.00 Completed.
Replacement of Existing Quay berths (EQ 2,3,4,5) to cater to 14.5m draft vessels 200.00 6.00 Work in progress. No delay
Kerala Cochin Construction of a liquid cargo jetty for coastal shipping vessels 45.00 3.00 Work in progress. No delay
Malabar Cement Terminal 160.00 1.00 Work in progress. No delay
Karnataka New Mangalore Provide Handling Equipment at Berth No. 12 (Old berth no.18) for Handling Bulk Cargo & Containers under PPP Mode. 469.46 6.15 Work in progress. No delay
Goa Mormugao Conversion of Berths 8,9 barge berths and MOHP as Multipurpose Cargo Berth 1100.00 14.00 Concession Agreement signed.
Maharashtra Mumbai Bunkering Terminal 50.00 2.00 Phase-I Completed
Fifth Oil Berth 811.00 20.00 Work in progress. No delay
Jawahar Lal Nehru Road Connectivity 6/8 laning 2787.00 - Work in progress. No delay
Procurement of 15 RTYGCs at port owned Container Terminal 200.00 6.60 6RTYGCs arrived at Port and remaining 9 are expected by September, 2017
Gujarat Kandla Construction of Oil Jetty No. 7 on BOT basis for liquid cargo. 72.00 2.00 Work has not been started for want of Environment Clearance.
Dredging to 18 meters of Dry Bulk Terminal, Tuna-Tekra 50.00 6.00 -do-
Deployment of two floating cranes (in addition to two floating cranes which is under completion) 60.00 2.00 Completed
Development, operation & maintenance of Container Terminal (Berth 11&12) on BOT basis 263.00 7.20 Completed
Status of projects awarded in the year 2016 -17
State Port Project Cost
(Rs. In crore) Capacity
(In million tonnes Per Annum) Status
Tamil Nadu Chennai Development of Coastal Terminal 80.00 1.10 Work in progress. No delay
Installation of 400 kw Solar power plant on building roof tops 3.79 - Work is progress. No delay
Development of Paved storage yards for handling Export Cargoes 54.00 - Work in progress. No delay
VoC Port
Turicorin Deployment of 2 Additional Harbour Mobile Cranes at III & IV berth 57.00 8.72 Order placed on 31.03.2017. Expected arrival is 30.11.2017.
Truck parking terminal 23.77 - Work in progress. No delay
Providing railway track between Marshalling Yard and Hare Island. 70.12 - Work in progress.
Supply, installation, commissioning and maintenance of 5 MW Solar power plant at VOCPT for a period of 10 years on power purchase system 30.00 5MW Work has not been started.
Upgradation of Coal Jetty 1& 2 106.00 18.00 LOA issued on 6.2.2017.
Development of a PPP berth for construction material 65.37 2.00 LOA issued on 5.5.2017.
NCB III restructuring proposal 55.00 10.22 Work is progress.
Kamarajar Modification of existing Iron Ore Terminal on “as is where is” basis to also handle Common User Coal 220.00 6.00
Work has not been commenced for want of Environment Clearance.
Improvement to internal roads and gate complex in KPL 30.00 - Work in progress. No delay
Widening of NCTPS and Port Access Road to 4 lane from the existing 2 lane road (7 kms) 200.00 - Work started as TNRDC to obtain all statutory clearance.
Construction of Container Pre-Stacking Yard in the area of Port access road 30.00 - Work in progress. No delay
West Bengal Kolkata Deployment of 2 floating cranes near Sagar 60.00 2.00 Work in progress. No delay
Development of hardstand storage area of 1.13 Lakh sqm inside dock 43.99 - Work in progress. No delay
Replacement of Fendering system of Lead-in-Jetty 44.81 - Work in progress. No delay
Maintenance dredging for a period of 5 years 1050.00 - Work Commenced
Improvement of existing road connecting Kolkata Port Trust to NH6 and Kolkata port Trust to nearby Industrial Cluster 15.20 - Completed
Creation of LNG facilities behind Jetty I. 200.00 0.20 Offer letter for lease of land issued on 30.03.2017.
Odisha Paradip 2 nos of harbour mobile cranes 80.00 2.50 Completed
Design, Engineering, Procurement & Supply, Erection, testing, Commissioning and O&M for 10 years of 10MW solar power plant 86.46 - Work in progress. No delay.
Development of Inland Water Terminal 80.00 2.50 Completed
Andhra Pradesh Vishakapatnam Replacement of two MHC in EQ 5&6 in Inner Harbour 39.00 - One MHC installed and commissioned Other one kept in abeyance due to shortage of cargo.
Providing 3rd Line near 14 lever goompty of NH Yard 2.56
- Work entrusted to M/s RITES
Improving the capacity utilization of OR-1 & OR-II and fertilizers berths 166.00 - LoI issued on 31.03.2017
2 new crane at VCTPL 150.00 - Work in progress.
Kerala Cochin Procurement of oil spill response equipment 10.45 - Partly completed.
Karnataka New Mangalore Development of 30 acres of stack yard and ancillary roads for parking of Ro-Ro cargoes and cars` 25.00 - Work is progress. No delay.
Goa Mormugao Development of Storage area for container 15.00 - Completed
S&T system for railway yard 12.18 - Work is progress. No delay.
Providing additional rail lines and paving 12.60 0.40 Work is progress. No delay.
Roof Top Solar Power system – 200 KW 1.90 - Completed
Maharashtra Mumbai Construction of breakwater at Mandwa (Maharashtra Maritime Board) 130.80 - Work is progress. No delay.
Construction of Ro-Ro Pax facility 30.60 - Work is progress. No delay.
Jawahar Lal Nehru SEZ Phase – EPC Contract for infrastructure development 468.82 - Work is progress. No delay.
Evacuation road for proposed standalone Container Terminal (330 extension to DPW terminal) 128.80 - Work is progress. No delay.
Capital Dredging – Phase – II 2029.00 20.87 Work has not been started. Mobilisation of dredgers and crew members are in progress.
Coastal berth 170.00 3.00 Work is progress. No delay.
Restructuring of container yard for optimal yard utilisation 200.00 - Work is progress. No delay.
Development of common rail yard with Rail over bridge 243.00 - Work is progress. No delay.
Flyover at Y junction for decongestion of Traffic Flow 80.00 - Work is progress. No delay.
Construction of Central Truck Parking Terminal 200.00 - Work is progress. No delay.
Augmentation of 220 KV/33KV Master unit substation for providing electrical power supply to Fourth container Terminal 39.10 - Work is progress. No delay.
Improvement in Road Connectivity by 6/8 Laning of NH 4B SH54 and Amra marg Phase II 335.91 - Work is progress. No delay.
Gujarat Kandla RoB on Kandla Kutch Road 232.62 - Work is progress. No delay.
Redevelopment of Berth 14&16 531.00 9.00 Work is progress. No delay.
Mechanisation of Fertiliser Handling Facility 12.33 2.68 Work is progress. No delay.
6 MV wind power project 65.00 - Completed
Mechanization of fertilizer handling, mechanized bagging and wagon loading 122.00 1.40 LOA issued on 31.03.2017
Container terminal at berth 11 and 12 Concession awarded 159.00 7.20
(0.60 million TEU p.a.) Completed
Providing rail connectivity to berth No. 13, 14, 15 & 16 from take-off point to west end of berth at Kandla Port. 101.29 - Work order issued. No delay.