Question : ROB IN MAHARASHTRA



(a) whether the Union Government have received a proposal from the Government of Maharashtra to construct over bridges in the State especially on the railway crossings in Vidarbha region;

(b) if so, the details thereof, project wise; and

(c) the time by which these overbridges are likely to be constructed?

Answer given by the minister

MINISTER OF STATE IN THE MINISTRY OF PARLIAMENTARY AFFAIRS AND MINISTER OF STATE IN THE MINISTRY OF RAILWAYS ( SHRI O. RAJAGOPAL )

(a) & (b) Construction of ROBs across busy level crossings is a continuous ongoing activity. Works which have to be sanctioned on cost sharing basis are processed by Zonal Railways on receipt of firm proposal along with required undertaking for cost sharing from State Govt. and sent to Railway Board for inclusion in Works Programme. Other cases for construction of ROBs on deposit/BOT basis are processed at Zonal Railway level and necessary sanction conveyed to State Govt. to take up the Work. Information about such works is not maintained region-wise, it is maintained state-wise. A list of on going ROBs works in Maharashtra State on cost sharing, deposit and BOT basis is enclosed as a statement at Annexure “A”. A list of ROBs under-consideration under BOT at Zonal Railway level is enclosed at Annexure ‘B’.

(c) Railway constructs the bridge proper (Across Railway track) and State Govt. constructs the approaches of ROBs. Railway will complete its portion of work before or along with the construction of approaches by the State Government.

ANNEXURE ‘A’

STATEMENT REFERRED TO IN REPLY TO PARTS (a) & (b) OF THE UNSTARRED QUESTION NO. 4071 BY SHRI NAMDEO HARBAJI DIWATHE TO BE ANSWERED ON 18.4.2002 IN LOK SABHA REGARDING ROB IN MAHARASHTRA

(a) & (b)

List of sanctioned works							(Rs. in lakhs)

S.No Name of Works Year of Sanction Rly’s State Share Share
1. ULHASNAGAR – ROB in lieu of LC no. 3-C Km. 57/9-10 KYN-Pune Sec. 1999-00 253 226

2. SHRIRAMPUR- RUB at Km 416/11-12 at DD-MMR Sec. 1999-00 51 51

3. Virar-ROB in lieu of L.C. No. 40 1999-00 579 850

4. Chembur – Widening of RUB at FCI circle at Km. 17/2-3 on CSTM-PNVL sec. 1999-00 BOT 465

5. Babupeth Km. 880/4-5 on WR-BPQ Section in lieu of lxing No. 44-A. 1999-00 BOT 1030 6. Kedgaon ROB in liew of L-xing No. 11-B at Km. 246/2-3 on PA-DD Section. 1999-00 BOT 399

7 Chalisgaon ROB at Km. 324/3-5 on IGP-BSL Sec. 1999-00 BOT 246

8. Anand Talkies RUB at Kms 835/29-31 on WR-NGP Section. 1999-00 BOT 610

9. Daund Km. 265/3-4 PA-DD Section in lieu of lxing No. 18-B 1999-00 BOT 1723 10. Bhivandi ROB on MB-NSK Express way NA 54/184 DIVA-VASAI Section 1999-00 BOT 149 11. Kopri ROB @ Km. 31/13-14 on CSTM-KYN Section 1999-00 Deposit 1273 12. NANDED-PATHENOR (H) – ROB at Km. 353/15-16 on Mudkhed-Purna section 1999-00 Deposit 194 13. BIMBARI-BHOKAR – ROB at Rly. Km. 20/4-5 on Mudkhed-Adilabad section. 1999-00 Deposit 120 14. Chikaltana-Karmad ROB at Rly Km. 160/5-6 (Jalna-Manmad) 1999-00 Deposit 0 15. Vitava (Thane) RUB widening at Km. 34/4-5 CSTM-KYN Section 1999-00 Deposit 460 16. Dhamangaon ROB at Kms. 709/19-21 1999-00 Deposit 74 17. Bund-garden Widening at km. 192/6-7 PA-DD Sec. PA Div. 1999-00 Deposit 267 18. Hinganghat ROB in lieu of LC No. 13/A at Km. 790/34-36 on WR-BPQ Sec. 2000-01 492 648 19. Santra market at Kms 837/1 Nagpur yard NGP Divn. 2000-01 BOT 1260 20. Ambernath ROB for MIDC at Kms. 62/14-15 on KYN-LNL sec. 2000-01 Deposit 217 21. KURDUWADI – ROB in lieu of LC No. 38-A at Km. 375/13-14 on Daund-Solapur section 2001-02 201 162 22. JEUR-ROB in lieu of LC No.33-A at 342/3-4 DD-SUR Section 2001-02 246 220 23. RAMWADI-ROB in lieu of LC No. 55-B at Km. 456/0-1 on Solapur-Wadi section 2001-02 258 232 24. NAVADE ROAD – ROB in lieu of LC No.12A at Km. 60/4-5 on Diva-Panvel section 2001-02 425 600 25. Kalanagar- CCG-VR:- KalaNagar ROB(On western express) – Proposed widening of ROB by four line (19.05 m) for BMRD at Km 14/4-5 on south Bandra station MMRDC 1985-86 Deposit 427 26. Chembur-ROB Widening of LC-NA at Km. 17/6-7 CSTM-PNVL Sec. 1994-95 Deposit 101 27. BADLAPUR-ROB in lieu of Lxing No. 10/B Kms 66/19-20 at KYN-LNL sec. 1995-96 269 333 28. Borivli-ROB in lieu of LC No.33 at North of stn. 1995-96 583 2108 29. Akurdi ROB at Km. 172/11-12 on LNL-PA sec. 1995-96 Deposit 158 30. Bombay-Ahmedabad (1/12.0 m span) RUB at km. 76.18 on NH-8 1995-96 Deposit 503 31. NIPHAD – ROB in lieu of Lxing No.99-B at Kms. 218/8-9 on IGP-BSL Section. 1996-97 174 115 32. Boisar-Palghar-ROB in lieu of LC No. 51. 1996-97 338 1736 33. Santacruz-Vile Parle- ROB in lieu LC No.21 1996-97 609 2513 34. Kandivali-Malad-ROB in lieu of LC No.31 1996-97 662 2024 35. NIMBOLA- ROB in lieu Lxing No. 175 Kms. 505/26-28 IGP-BSL sec 1996-97 96 156 36. Murtizapur ROB in lieu of L-Xing No.51 (BG) at Kms.62/6-7 on BSL-BD sec. 1996-97 BOT 319 37. Sancheti hospital, Widening of ROB near Shivaji Nagar, Pune 1996-97 Deposit 86 38. Alankar talkies widening of ROB near Pune @ Kms. 191/19-20 PA-DD Sec. 1996-97 Deposit 144 39. Chunabhati- ROB in lieu of L xing no. 1-HB 13/12-13 MB-BR Sec. 1997-98 128 176 40. Sewri-ROB in lieu of LXing no. 7-A at 7/3-4 MB-BR Sec. 1997-98 195 521 41. Vikhroli ROB in lieu of LXing no. 14-C at 22/11-12 MB-Thane section. 1997-98 242 337 42. Bhayander-ROB in lieu of L.C. No.35 & 5m wide FOB with ramp 1997-98 495 1580 43. Ambad-Naka ROB @ Km. 174/14-15 between Dinagaon-Jalna (L.C. No.77). (Parbhani-Manmad section) 1997-98 Deposit 138 44. Kurla, Santacruz-Chembur link road crossing Rly. track 1997-98 Deposit 3590.2 45. Stanvac Nagar ROB at km. 19/13-14 on CSTM-KYNsec. 1997-98 Deposit 857 46. ROB at Phursungi in lieu of LC No.9 at Km. 11/11-12 on PA-MRJ Section 1998-99 BOT 110 47. ROB at Shelgaon in lieu of LC No.71 at Km.161/2-3 in Manmad – Parbhani section on AWB-Jalna road 1998-99 BOT 665 48. ROB at Rotegeon in lieu of LC No.22 at Km. 52/1-2 on MMR-PBN section 1998-99 BOT 260 49. ROB at Jejuri in lieu of LC no.20 at Km. 58/9-10 on PA-MRJ Section 1998-99 BOT 120 50. ROB near Parbhani at km. 289/07-09 in LC No. 121/E at Km. 289/11-12 1998-99 BOT 110 51. ROB at Ladgaon in lieu of LC No. 61 at Km. 133/7-8 in Manmad-Parbhani section on AWB-Jalna Road 1998-99 BOT 803 52. ROB at Ichalkaranji in lieu of LC No.20 at Km. 31/11-12 on MRJ-KOP section 1998-99 BOT 70 53. Vivekanand Nagar-ROB in lieu of LC No. 40-A at Km. 872/16-17 on WR-BPQ Sec. 1998-99 Deposit 275 54. Tadali Main Km 860/14-15 on WR-BPQ Section in lieu of lxing No. 38-A 1998-99 BOT 820 55. Chandrapur Km. 875/6-7 on WR-BPQ Section in lieu of l.Xing No. 41-A 1998-99 BOT 1000 56. Naigaon-ROB at Naigaon MSRDC 1998-99 BOT 0 57. VR-ST:- Virar ROB in lieu of LC No.41 (state PWD) 1998-99 BOT 58. ROB at Zalta in lieu of LC no.5 at Km. 124/15-16 on in Manmad-Parbhani section AWB-Jalna Bye-pass road 1998-99 BOT 800 59. Ghatkopar, Widening of existing ROB at Km. 18/15-16 on CSTM-KYN Sec 1998-99 Deposit 176 60. Pimpri-Chinchwad, Widening of ROB at Km. 175/12-13 on LNL-PA sec. 1998-99 Deposit 242 61. Kalyan (Patripool) ROB at Km. 51/16-17 on CSTM-KYN Sec. 1998-99 Deposit 308

ANNEXURE ‘B’

List of ROB Works on BOT/Deposit basis under consideration


1. ROB at Manakpur in lieu of LC No. 295 at Kms 1038/26-28

2. ROB at Mekasobaugh in lieu of LC No. 296/A at Kms. 1040/15-17

3. ROB at Mangalwari Bazar in lieu of LC No. 297 at Kms. 1042/00

4. ROB at Wadrha byepass in lieu of LC No. 89/C at Kms. 756/8-10

5. ROB at Akola-Gaigaon in lieu of LC No. 36/A at Kms. 597/12-14 6. ROB at Warora in lieu of LC No. 28/B at Kms. 831/13-15

7 ROB at Butibori in lieu of LC No. 113/A at Kms. 812/26-28

8. ROB at Shegaon in lieu of LC No. 27/B at Kms. 547/52-54

9. ROB at Nandura in lieu of LC No. 20/A at Kms. 522/20-22 10. ROB at Dhamangaon at Kms. 709/19-20