THE MINISTER OF STATE IN THE MINISTRY OF URBAN DEVELOPMENT (SMT. DEEPA DASMUNSHI)
(a) to (g) The details of schemes implemented by Ministry of Urban Development for Mumbai so
as to upgrade water supply, sewerage system, drainage system, roads & flyovers etc. are as
under: -
(i) Under Urban Infrastructure & Governance (UIG), a sub-mission of Jawaharlal Nehru National
Urban Renewal Mission (JNNURM), 26 projects have been sanctioned for Mumbai at a total cost of
5358.48 crore wherein Additional Central Assistance (ACA) committed is 1875.47 crore. ACA of
1635.86 crore has been released.
Government has approved the proposal of Ministry of Urban Development to mandate continuation
of JNNURM to sanction new project and capacity building activities till 31st March 2014.
(ii) Under the second stimulus package announced by the Government of India in January, 2009,
the States, including Maharashtra, as a one-time measure have been provided financial assistance
for purchase of buses for their urban transport system under the scheme for providing central
financial assistance for procurement of buses for urban transport under JNNURM. The financing
is meant exclusively for City Bus Service and Bus Rapid Transit System (BRTS) for all Mission
Cities.
The Brihan Mumbai Electric Supply & Transport Undertaking (BEST) and Navi Mumbai have been
sanctioned 1150 modern Intelligent Transport System (ITS) enabled buses under JnNURM. Details
are as under:
(Rs. in crore)
S. City / Total Fleet Total Cost Delivery of Central Total
No Organisation sanctioned Approved buses Share (ACA) released in CSMC Approved
1 BEST 1000 284 1000 99.40 57.85
2 Navi Mumbai 150 40.5 150 14.18 12.16
(iii) Two metro rail projects on Public Private Partnership (PPP) mode and one Metro Rail
Project on Joint Venture between Centre and State Government in the state of Maharashtra have
been approved. The details are as under:
S. Project Project Details Present Fund
No. Status Sanctioned /released
1 Mumbai Metro Rail The total length Overall 85% Out of total Project Line-1 of the corridor work has been Viability Versova-Andheri- is 11.40 km and completed and the Gap Funding (VGF) Ghatkopar Corridor completion cost line is likely to grant of ` 471 is 2356.00 cr. be commissioned by crore, Central The project is later half of the Government has under implementation year 2013. released ` 235.50 on Public Private crore and 75 crore Partnership (PPP)/ during the BOOT format by financial year Mumbai Metro which 2009-10 & 2011-12 is a Joint Venture respectively of M/s Reliance Infrastructure Ltd., M/s Veolia and Mumbai Metropolitan Region Development Authority (MMRDA). The Central Government has approved VGF amounting to 20% of the project cost i.e. ` 471 crore as special Additional Central Assistance (ACA)
2 Mumbai Metro Line-2 The total length of Project has been Government of (Maharashtra) the corridor is 31 approved, however India has approved Charkop-Bandra- .871 km and the , work is not 1532 crore VGF Mankurd Corridor estimated completion yet started. however not yet cost is 7660.00 released. crore. Line-2 is a joint Venture comprising M/s Reliance Infrastruc ture Ltd., SNC Lavalin, Canada & Reliance Communi cation Ltd.
(iv) The Brihan Mumbai Storm Water Drainage (BRIMSTOWAD) Project, for improvement of storm water
drainage in Mumbai was approved on 12.07.2007 at an estimated cost of ` 1200.53 crore out of
which an amount of ` 1000 crore has already been released.