(a) the details and the present status of Gajulamandyam to Chennai Highway Project along with the cost thereof;
(b) the date on which the work on the said project was awarded; and
(c) the time by which the said project is likely to be completed?
(a) the details and the present status of Gajulamandyam to Chennai Highway Project along with the cost thereof;
(b) the date on which the work on the said project was awarded; and
(c) the time by which the said project is likely to be completed?
THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (c) The work for augmentation of Tirupati-Tiruthani-Chennai Section of NH-205 was awarded to M/s. Transstroy Tirupati-Tiruthani-Chennai Tollways Pvt. Ltd. on BOT (Toll) on 30.04.2010 with Total Project Cost (TPC) of about Rs. 571 crores. Out of the total length of 124.70 km, the Concessionaire has completed 100.930 km. As per National Company Law Tribunal (NCLT) order dated 03.06.2019, Corporate Insolvency Resolution Process (CIRP) has been initiated against the Concessionaire. The bid process for balance works on this project stretch has been initiated. However, in view of the process initiated as per NCLT order, the date of completion of these balance works has not been decided.
*****