THE MINISTER OF INFORMATION AND BROADCASTING AND PARLIAMENTARY AFFAIRS (SHRI P. R. DASMUNSI)
(a), (b) & (c) : Yes, Sir. State-wise details in respect of the new TV centre projects and augmentation of the existing TV Centres are given at the Annexure.
(d) : Progress of the projects is generally satisfactory.
ANNEXURE
ANNEXURE REFFERED TO IN REPLY TO PART (a), (b) & (c) OF THE LOK SABHA UNSTARRED QUESTION NO.792 FOR 31.07.2006.
TV Centre Projects
New TV Centres Status
1. Studio, Rajouri Technically ready.
2. Studio, Calicut Technically ready.
3. Studio, Tirupati Site taken over. Building plans finalised. Target date: 2008-09.
Augmentation of
Existing TV Centres.
1. Studio, Gorakhpur Technical area of building completed. Departmental (pmt set up) works taken up. Target date : 2006-07.
2. Studio, Derhadun Land taken over. Building plan finalized. Preliminary (pmt set up) estimate for building works under process of sanction. Target date: 2008-09.
3. Studio, Leh Work of building construction awarded. Target date: (pmt set up) 2008-09.
4. Studio, Chandigarh Building plan finalized. Preliminary estimate for (addl. Studio) building works under process of sanction. Target date : 2008-09.
5. Studio, Panaji Building plan finalized. Preliminary estimate for (addl. Studio) building works sanctioned. Target date : 2008-09.
6. Studio, Jammu Building plan finalized. Preliminary estimate for (addl. Studio) building works sanctioned. Target date : 2008-09.
7. Studio, Srinagar(aug.) Building plan finalized. Preliminary estimate for building construction sanctioned. Target date: 2008-09.
8. Studio, Portblair(aug.) Scheme recently approved. Financial sanction issued. Building plan under preparation. Target date : 2007-08.