THE MINISTER OF POWER
( SHRI SUSHILKUMAR SHINDE )
(a) to (d) : A Statement is laid on the Table of the House.
STATEMENT
STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (d) OF
STARRED QUESTION NO. 320 TO BE ANSWERED IN THE LOK
SABHA ON 19.12.2008 REGARDING POWER TRANSMISSION
LINES.
(a) to (c) : The Central Electricity Authority (CEA) has finalized
the programme for laying of power transmission lines in the country
in tandem with the capacity addition programme during the 11th Five
Year Plan. The construction of a transmission system is a dynamic
programme. It has to correspond to addition in generation capacity.
In case of any change in the programme of commissioning of
generation projects, a rigorous continuing exercise is carried out to
reschedule the programme of transmission works to match the
commissioning of generation projects. The programme and the
percentage of work completed by October, 2008 are given below:
Transmission Lines Programme Achievement Percentage ( 11th Plan) Upto October Achievement (2007-2012) 2008
Central Sector (ckm) 55360 9257 16.72
State Sector (ckm) 40200 8418 20.94
TOTAL (ckm) 95,560 17,675 18.49
(d) : The following steps are being taken to achieve the
targets:
(i) Comprehensive monitoring is done by the Ministry of Power
and Central Electricity Authority by convening project
review meetings at regular intervals to assess the critical
areas, project interface problems and completion trends etc.
to take pre-emptive measures and advance action on various
project linked activities.
(ii) Project execution is also monitored at field level and at
corporate level by the respective executing agencies.
(iii) Bottlenecks faced by the executing agencies are sought to
be resolved by taking timely action with the concerned
authorities in respect of forest clearances, railway
clearances, Right of Way (ROW) problems etc.