(a) whether survey work for doubling of Bandel-Katwa rail line of Eastern Railways has been completed;
(b) if so, the details thereof; and
(c) if not, the time by which the work is likely to be started?
(a) whether survey work for doubling of Bandel-Katwa rail line of Eastern Railways has been completed;
(b) if so, the details thereof; and
(c) if not, the time by which the work is likely to be started?
MINISTER OF STATE IN THE MINISTRY OF RAILWAYS ( SHRI DIGVIJAY SINGH)
(a) : Yes, Sir.
(b) & (c): The results of the survey have revealed cost of doubling of the 105 km. long line is Rs. 208.41 cr.