Question : Optical Fibre Cable Network

(a) the completion/pending details of Optical Fibre Cable (OFC) network in the country since 2014 onwards till date; and

(b) the funds sanctioned/spent therefor till now, State-wise including Andhra Pradesh and Telangana?

Answer given by the minister

MINISTER OF STATE FOR COMMUNICATIONS
(SHRI DEVUSINH CHAUHAN)

(a) BharatNet project is implemented in a phased manner to provide broadband connectivity to all the Gram Panchayats (GPs) in the country through an optimal mix of media (OFC/Radio/Satellite). Since 2014, out of about 7,40,706 km planned OFC, 5,67,941 km OFC has been laid, under the project as on 28.02.2022.

(b) The State-wise total funds allocated/sanctioned/disbursed under BharatNet Project, including Andhra Pradesh and Telangana, are given in Annexure-I.

Download PDF Files