(a) the details of present status of on-going Rail Over Bridge/Rail Under Bridge projects in Kerala, project-wise;
(b) the expenditure incurred on each of these ROB/RUBs so far; and
(c) the time by which these ROB/RUBs are likely to be completed?
(a) the details of present status of on-going Rail Over Bridge/Rail Under Bridge projects in Kerala, project-wise;
(b) the expenditure incurred on each of these ROB/RUBs so far; and
(c) the time by which these ROB/RUBs are likely to be completed?
MINISTER OF STATE IN THE MINISTRY OF PARLIAMENTARY AFFAIRS AND MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI O. RAJAGOPAL)
(a) & (b): Statement is attached.
(c): Railway will complete its part of the work i.e. the bridge proper over rail track before, or alongwith, completion of work on approaches by State Government.
Statement
Status of ROBs/RUBs works on cost sharing basis.
(Rs. in lakhs)
Sl.No. Name of Work Railways State Expd. Present status share Govts. incurred share by Railways upto 31.1.2002
1 Cheravatur ROB in lieu of 511 499 9 Estimate under preparation LC No.269 at Km.805/5-6 in Shoranur-Mangalore section between Cheravattur and Nileshwar stations
2 Padanakkad ROB in lieu of 511 499 10 Estimate under preparation LC No.810/1-2 in Shoranur- Mangalore section between Kanhangadi and Nileshwar stations
3 Cherrode ROB in lieu of 311 389 72 Work in progress LC No.215 @Km.713/10-11 in Shoranur-Calicut section on NH 17 at Km. 196/425
4 Chalakudi ROB in lieu of 753 746 10 Work in progress LC No.48 at Km. 62/9-10 in Shoranur-Ernakulam section
5 Vengalam ROB in lieu of 499 499 12 Work in progress LC No.196 at Km. 675/1-2 in Shoranur-Mangalore section between Elattur and Quilandi stations on NH 17 at Km.231/625
6 Vengali ROB in lieu of 581 581 11 Work in progress LC No.192 @ Km. 673/8-9 in Shoranur-Mangalore section between West Hills and Elattur stations on NH 17 at Km.237/600
7 Velayyil ROB in lieu of 850 844 2 Work in progress LC No.186 at Km. 666/11-12 in Shoranur-Mangalore section between Calicut and West Hills stations on NH 17 Beach Road
8 Nandal ROB in lieu of 511 499 10 Estimate under preparation LC No.239 at Km. 749/2-3 in Shoranur-Mangalore section between Ettakot and Cannanore stations on NH 17 at Km.166/400
9 Chova ROB in lieu of 511 499 12 Estimate under preparation LC No.238 at Km. 695/12-13 in Shoranur-Mangalore section between Ettakot and Cannanore stations on NH 17 at Km.160/550
10 Nandi ROB in lieu of 610 610 10 Work in progress LC No.206 at Km. 695/12-13 in Shoranur-Mangalore section between Ettakot and Cannanore stations on NH 17 at Km.214/525
11 Chengottukavu ROB in lieu of 606 606 11 Work in progress LC No.199 at Km. 686/1-2 in Shoranur-Mangalore section between Elathur and Quilandi stations in NH 17 at Km.224/170
12 Muzhuppilangadi ROB in lieu of 626 626 9 Work in progress LC No.232 at Km. 738/7-8 in Shoranur-Mangalore section between Dharmadam and Ettakot stations on NH 17 at Km.171/450
13 Irinjalakuda ROB in lieu of 629 622 1 Work in progress LC No.43 at Km. 56/9-10 in Shoranur-Ernakulam section
14 Iddappalli ROB in lieu of 742 736 0 Details such as LC No.71 at Km. 102/13-14 longitudinal section between Iddappalli and and cross section is ERS stations awaited from State Government.
15 Angamali ROB in lieu of 538 534 0 Site plan, LS is awaited LC No.64 at Km. 80/12-13 in from State Government. Shoranur-Ernakulam section
16 Payyanur ROB in lieu of 538 534 0 Work is being done by LC No.271 at Km. 807/6-7 in RBDCK.Work is in progress. Shoranur-Mangalore section
17 Ferok-Kallayi ROB in lieu of 538 534 0 Work is being done by LC No.177 at Km. 600/4-5 on RBDCK.Work is in progress. NH 17 Beypore State Road
18 Tirunetur ROB in lieu of 524 518 0 GAD and site plan awaited LC No.76T at Km. 1/9-10 from State Government. between Ernakulam and Tirunetur stations
19 Ernakulam ROB in lieu of 524 518 0 GAD and site plan awaited LC No.2 at Km. 3/19-20 from State Government. between Ernakulam and Quilon stations
20 Tirur ROB in lieu of 571 560 0 Site plan and LS awaited LC No.174 at Km.639/14-15 in from State Government. Shoranur-Mangalore section on NH 17 (Tirur Calicut State Highway)
21 Kuttipuram ROB in lieu of 538 534 0 Work is being done by LC No.171 at Km.626/10-11 in RBDCK.Work is in progress. Shoranur-Mangalore section on NH 17 (Tirur Calicut State Highway)
22 Korattiyangadi ROB in lieu of 538 534 0 Work is being done by LC No.54 at Km.67/13-14 in RBDCK.Work is in progress. Shoranur-Ernakulam section
23 Mundoor Road ROB in lieu of 538 534 0 Work is being done by LC No.26 at Km.39/13-14 in RBDCK.Work is in progress. Shoranur-Ernakulam section
24 Ollur ROB in lieu of 571 559 0 Site plan and LS awaited LC No.17 at Km.28/10-11 in from State Government. Shoranur-Ernakulam section
25 Kalamasserry-Iddappalli ROB 538 534 0 Work is being done by in lieu of LC No.67 at RBDCK.Work is in progress. Km.95/7-8 in Shoranur- Ernakulam section
26 Badagara ROB in lieu of 538 534 0 Kerala Government has LC No.229 at Km.732/9-10 in requested for deletion of Shoranur-Mangalore section this work from the works between Kolassery-Thalassery programme. Road stations
27 Irumpanam ROB in lieu of 571 559 0 Work is being done by LC at Km.8/15-16 in RBDCK.Work is in progress. Ernakulam-Quilon section
28 Pullapady ROB in lieu of 560 942 0 Work is in planning stage. LC No.73 at Km.105/5-6 Details awaited from State Government.
29 Palghat Town ROB in lieu of 524 518 0 Estimate under preparation LC No.50 at Km.54/12-13 between Palghat Town and Pollachi stations
30 Idapally-Ernakulam ROB 590.1 571.6 0 Taken up in combination in lieu of LC No.69A at with LC 71 at Pachalam. Km.101/10-11
31 Wadakancheri ROB in lieu of 590.10 571.6 0 Estimate under preparation LC No.13 at Km.21/5-6 Detailed road approach between Wadakancheri and cost awaited from State Mulagunathukavu section Government.
32 Kanjikode ROB in lieu of 590.10 571.6 0 Estimate under preparation LC No.159 at Km.531/8-10 Detailed road approach between Kanjikode-Palghat cost awaited from State stations Government.
33 Wasthil ROB in lieu of 587.60 576.1 0 Estimate under preparation LC No.201 at Km.688/2-3 Detailed road approach between Elathur and Quilandi cost awaited from State stations on Thalamassery- Government. Quilandy State Highway
34 Pallikera-Kottikulam ROB 587.60 576.1 0 Estimate under detailed in lieu of LC No.276 at Km. road approach cost awaited 825/15-826/1 from State Government.
35 Pollachi Pudunagaram 525.82 519.8 0 Estimate under preparation ROB in lieu of LC No.49 with State Government. at Km.53/10-11 Detailed road approach cost awaited from State Government.
36 Palghat-Palghat Town ROB 555.30 547.6 0 This ROB is very close in lieu of LC No.52 at Km. to existing weak Bridge. 56/4-5 Further investigation is being done.
37 Quilon-Mayyanad ROB in lieu 587.60 576.1 0 Instead of LC 543 of LC No.541 at Km.156/8-9 originally sanctioned. Detailed road approach cost awaited from State Government.