Question : OVER BRIDGES IN KERALA



(a) the details of present status of on-going Rail Over Bridge/Rail Under Bridge projects in Kerala, project-wise;

(b) the expenditure incurred on each of these ROB/RUBs so far; and

(c) the time by which these ROB/RUBs are likely to be completed?

Answer given by the minister

MINISTER OF STATE IN THE MINISTRY OF PARLIAMENTARY AFFAIRS AND MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI O. RAJAGOPAL)

(a) & (b): Statement is attached.

(c): Railway will complete its part of the work i.e. the bridge proper over rail track before, or alongwith, completion of work on approaches by State Government.

Statement

Status of ROBs/RUBs works on cost sharing basis.

(Rs. in lakhs)
Sl.No. Name of Work Railways State Expd. Present status share Govts. incurred share by Railways upto 31.1.2002
1 Cheravatur ROB in lieu of 511 499 9 Estimate under preparation LC No.269 at Km.805/5-6 in Shoranur-Mangalore section between Cheravattur and Nileshwar stations
2 Padanakkad ROB in lieu of 511 499 10 Estimate under preparation LC No.810/1-2 in Shoranur- Mangalore section between Kanhangadi and Nileshwar stations
3 Cherrode ROB in lieu of 311 389 72 Work in progress LC No.215 @Km.713/10-11 in Shoranur-Calicut section on NH 17 at Km. 196/425
4 Chalakudi ROB in lieu of 753 746 10 Work in progress LC No.48 at Km. 62/9-10 in Shoranur-Ernakulam section
5 Vengalam ROB in lieu of 499 499 12 Work in progress LC No.196 at Km. 675/1-2 in Shoranur-Mangalore section between Elattur and Quilandi stations on NH 17 at Km.231/625
6 Vengali ROB in lieu of 581 581 11 Work in progress LC No.192 @ Km. 673/8-9 in Shoranur-Mangalore section between West Hills and Elattur stations on NH 17 at Km.237/600
7 Velayyil ROB in lieu of 850 844 2 Work in progress LC No.186 at Km. 666/11-12 in Shoranur-Mangalore section between Calicut and West Hills stations on NH 17 Beach Road
8 Nandal ROB in lieu of 511 499 10 Estimate under preparation LC No.239 at Km. 749/2-3 in Shoranur-Mangalore section between Ettakot and Cannanore stations on NH 17 at Km.166/400
9 Chova ROB in lieu of 511 499 12 Estimate under preparation LC No.238 at Km. 695/12-13 in Shoranur-Mangalore section between Ettakot and Cannanore stations on NH 17 at Km.160/550
10 Nandi ROB in lieu of 610 610 10 Work in progress LC No.206 at Km. 695/12-13 in Shoranur-Mangalore section between Ettakot and Cannanore stations on NH 17 at Km.214/525
11 Chengottukavu ROB in lieu of 606 606 11 Work in progress LC No.199 at Km. 686/1-2 in Shoranur-Mangalore section between Elathur and Quilandi stations in NH 17 at Km.224/170
12 Muzhuppilangadi ROB in lieu of 626 626 9 Work in progress LC No.232 at Km. 738/7-8 in Shoranur-Mangalore section between Dharmadam and Ettakot stations on NH 17 at Km.171/450
13 Irinjalakuda ROB in lieu of 629 622 1 Work in progress LC No.43 at Km. 56/9-10 in Shoranur-Ernakulam section
14 Iddappalli ROB in lieu of 742 736 0 Details such as LC No.71 at Km. 102/13-14 longitudinal section between Iddappalli and and cross section is ERS stations awaited from State Government.
15 Angamali ROB in lieu of 538 534 0 Site plan, LS is awaited LC No.64 at Km. 80/12-13 in from State Government. Shoranur-Ernakulam section
16 Payyanur ROB in lieu of 538 534 0 Work is being done by LC No.271 at Km. 807/6-7 in RBDCK.Work is in progress. Shoranur-Mangalore section
17 Ferok-Kallayi ROB in lieu of 538 534 0 Work is being done by LC No.177 at Km. 600/4-5 on RBDCK.Work is in progress. NH 17 Beypore State Road
18 Tirunetur ROB in lieu of 524 518 0 GAD and site plan awaited LC No.76T at Km. 1/9-10 from State Government. between Ernakulam and Tirunetur stations
19 Ernakulam ROB in lieu of 524 518 0 GAD and site plan awaited LC No.2 at Km. 3/19-20 from State Government. between Ernakulam and Quilon stations
20 Tirur ROB in lieu of 571 560 0 Site plan and LS awaited LC No.174 at Km.639/14-15 in from State Government. Shoranur-Mangalore section on NH 17 (Tirur Calicut State Highway)
21 Kuttipuram ROB in lieu of 538 534 0 Work is being done by LC No.171 at Km.626/10-11 in RBDCK.Work is in progress. Shoranur-Mangalore section on NH 17 (Tirur Calicut State Highway)
22 Korattiyangadi ROB in lieu of 538 534 0 Work is being done by LC No.54 at Km.67/13-14 in RBDCK.Work is in progress. Shoranur-Ernakulam section
23 Mundoor Road ROB in lieu of 538 534 0 Work is being done by LC No.26 at Km.39/13-14 in RBDCK.Work is in progress. Shoranur-Ernakulam section
24 Ollur ROB in lieu of 571 559 0 Site plan and LS awaited LC No.17 at Km.28/10-11 in from State Government. Shoranur-Ernakulam section
25 Kalamasserry-Iddappalli ROB 538 534 0 Work is being done by in lieu of LC No.67 at RBDCK.Work is in progress. Km.95/7-8 in Shoranur- Ernakulam section
26 Badagara ROB in lieu of 538 534 0 Kerala Government has LC No.229 at Km.732/9-10 in requested for deletion of Shoranur-Mangalore section this work from the works between Kolassery-Thalassery programme. Road stations
27 Irumpanam ROB in lieu of 571 559 0 Work is being done by LC at Km.8/15-16 in RBDCK.Work is in progress. Ernakulam-Quilon section
28 Pullapady ROB in lieu of 560 942 0 Work is in planning stage. LC No.73 at Km.105/5-6 Details awaited from State Government.
29 Palghat Town ROB in lieu of 524 518 0 Estimate under preparation LC No.50 at Km.54/12-13 between Palghat Town and Pollachi stations
30 Idapally-Ernakulam ROB 590.1 571.6 0 Taken up in combination in lieu of LC No.69A at with LC 71 at Pachalam. Km.101/10-11
31 Wadakancheri ROB in lieu of 590.10 571.6 0 Estimate under preparation LC No.13 at Km.21/5-6 Detailed road approach between Wadakancheri and cost awaited from State Mulagunathukavu section Government.
32 Kanjikode ROB in lieu of 590.10 571.6 0 Estimate under preparation LC No.159 at Km.531/8-10 Detailed road approach between Kanjikode-Palghat cost awaited from State stations Government.
33 Wasthil ROB in lieu of 587.60 576.1 0 Estimate under preparation LC No.201 at Km.688/2-3 Detailed road approach between Elathur and Quilandi cost awaited from State stations on Thalamassery- Government. Quilandy State Highway
34 Pallikera-Kottikulam ROB 587.60 576.1 0 Estimate under detailed in lieu of LC No.276 at Km. road approach cost awaited 825/15-826/1 from State Government.
35 Pollachi Pudunagaram 525.82 519.8 0 Estimate under preparation ROB in lieu of LC No.49 with State Government. at Km.53/10-11 Detailed road approach cost awaited from State Government.
36 Palghat-Palghat Town ROB 555.30 547.6 0 This ROB is very close in lieu of LC No.52 at Km. to existing weak Bridge. 56/4-5 Further investigation is being done.
37 Quilon-Mayyanad ROB in lieu 587.60 576.1 0 Instead of LC 543 of LC No.541 at Km.156/8-9 originally sanctioned. Detailed road approach cost awaited from State Government.