Question : IRRIGATION PROJECTS PENDING CLEARANCE IN M.P



(a) the number of irrigation projects of Madhya Pradesh pending with the Union Government alongwith the period, name of each of these projects and their estimated cost;

(b) the amount spent by Madhya Pradesh Government on each of these projects; and

(c) the time by which the projects are likely to be cleared by the Union Government for irrigation in the State alongwith the names of the projects?

Answer given by the minister


MINISTER OF STATE IN THE MINISTRY OF ENVIRONMENT AND FORESTS (SHRI BABU LAL MARANDI)

(a) & (c) No proposal from Madhya Pradesh is pending in the Ministry for environmental clearance under Environment (Protection) Act, 1986.

The details of the 7 proposals (received from Madhya Pradesh in the last five years), which are pending for forest clearance under the Forest (Conservation) Act, 1980 is annexed.

(b) The Ministry of Environment & Forests does not monitor the amount spent on the projects/proposals, which are received for clearances. It monitors the compliance of conditions laid out in the forest and/or environmental clearances only.

ANNEXURE

STATEMENT IN RESPECT OF PARTS (a) AND (c) OF THE LOK SABHA UNSTARRED QUESTION NO. 4549 ON ` IRRIGATION PROJECTS PENDING CLEARANCE IN M.P.` FOR 24.4.2000.

S.NO.	NAME OF PROPOSAL	COST AS PER THE	REMARKS	PROPOSAL (Rs.)
1 Indira Sagar Pariyojana Canal, 2167.67 crores The proposal was received from Khandwa (part of Narmada Sagar (for the whole the State Government on 16.2.95. Project) Narmada Sagar Essential details have been Project) sought from the State Govt. on 23.2.95. Reminded on 2.9.1999. Only on receipt of the essential details the proposal can be processed further.
2 Danmarhi Tank Project, Vidisha 1.02 crores The proposal was received on 13.5.97 and was rejected on 26.10.98. However, on request of the State Government, the proposal is being reconsidered.
3 Amanalla Tank Project, Balaghat 2.24 crores The proposal was received from the State Government on 19.5.97. Essential details have been sought from the State Govt. on 21.5.97 & 11.11.98. Reminded on 11.10.99. Only on receipt of the essential details the proposal can be processed further.
4 Bijasan tank project, Khargone 2.94 crores The proposal was received from the State Govt. on 30.10.98. Essential details have been sought from the State Govt. on 24.2.99. Reminded on 27.9.99. Only on receipt of the essential details the proposal can be processed further.
5 Sagad minor irrigation project,Vidisha 31.30 crores The proposal was received from the State Government on 5.3.99. Essential details have been sought from the State Govt. on 2.7.1999. Only on receipt of the essential details the proposal can be processed further.
6 Ratapani irrigation project, Raisen Not available The proposal is under active consideration of the Ministry.
7 Sumeri tank project, Guna 4.70 crores The proposal was received from the State Government on 28.7.99. Essential details have been sought from the State Govt. on 16.8.99. Only on receipt of the essential details the proposal can be processed further.