Question : DAIRY DEVELOPMENT PROGRAMME



(a) whether the Union Government has received a proposal from the State Government of Madhya Pradesh under the Intensive Dairy Development Programme;

(b) if so, the details thereof;

(c) the time by which the scheme is likely to be implemented fully; and

(d) the funds earmarked and released by the Union Government thereon?

Answer given by the minister


THE MINSTER OF STATE FOR AGRICULTURE AND FOOD PROCESSING INDUSTRIES (Dr. CHARAN DAS MAHANT)

(a) Yes, Madam

(b) to (d) Government of Madhya Pradesh submitted six project proposals under Intensive Dairy Development Programme (FDDP). These six projects have been approved at a total cost of Rs.3806.62 lakh by Department of Animal Husbandry, Dairying 8t Fisheries, Government of India. Details are given as under:

(Rs. in iakh)
SI.No. District covered Date of Approval Approved Total Status and Project period# outlay Fund released
1 Guna & Narsinghpur 1993-94 to 2007-08 494.06 494.06 Completed
2 Khargaon, Chattarpur, 07.03.1996 475.28 475.28 Completed Satna & Rewa 1995-96 to 2007-08
3 Jhabua 29.09.2005 228.89 192.44 On-going 2005-06 to 2008
4 Chhindwara and Balaghat 29.09.2005 420.58 361.77 On-going 2005-06 to 2007-08
5 Harda,Barwani,Neemuch, 30.03.2007 1422.09 743.27 On-going Sheopur & Seoni 2006-07 to 2009-10
6 Dewas, Dhar, 16.02.2012 765.72 356.34 On-going Khandwa & Betul 2011-12 to 2013-14
3806.62 2623.16

# Time of full implementation depends upon complete utilisation of funds by the implementing agency as per the approved project.