Question : HYDRO POWER PROJECTS IN NORTH-EAST REGION



(a) whether the Government have planned to set up 25,000 MW hydro power projects in North-East Region;

(b) if so, the details of steps taken in this regard;

(c) the present installed capacity of Hydel power in the region; and

(d) details of number of on going projects and time by which they are likely to start generate power?

Answer given by the minister

THE MINISTER OF STATE IN THE MINISTRY OF POWER ( SHRIMATI JAYAWANTI MEHTA )

(a) : Government have planned hydro capacity addition of 349 MW in North Eastern Region during 10th Plan and 8380 MW during 11th Plan. Under 50,000 MW Hydro Electric Initiative launched in May, 2003, works relating to preparation of Preliminary Feasibility Reports of 60 schemes with an aggregate installed capacity of 30427 MW in North Eastern Region have been entrusted to different agencies.

(b) : A number of projects have been planned by the Government for implementation in the North Eastern Region. Some of the major projects are listed in Annex-I. Preliminary Feasibility Report in respect of 60 schemes with an estimated installed capacity of about 30,427 MW are to be prepared by different agencies in the Central / State Sector in North Eastern region as per details given below:

Sl.	Name of State	No. of Scheme	I.C. (MW)
No.
1. Arunachal Pradesh 42 25690

2. Manipur 3 407

3. Meghalaya 9 1490

4. Nagaland 3 970

5. Mizoram 3 1870
Total = 60 30427


(c) : As on 31.07.2003, the installed capacity of existing HE. Projects in N.E. Region is 1070 MW (considering H.E. schemes of capacity more than 3 MW).

(d) : At present, 5 nos. of schemes aggregating to an installed capacity of 359 MW are under construction as per details given below:
Sl.	Name of Scheme	Installed Capacity	Likely Benefits
No
1. Myntdu (Leshka), Stage-I, 2 x 42 = 84 MW 10th Plan Meghalaya

2. Karbi Langpi 2 x 50 = 100 MW 10th Plan (Lower Borpani), Assam

3. Kopili Stage-II, Assam 1 x 25 = 25 MW 10th Plan
4. Tuirial, Mizoram 2 x 30 = 60 MW 10th Plan
5. Loktak Downstream 90 MW 11th Plan

ANNEX-I

ANNEX REFERRED TO IN REPLY TO PART (b) OF UNSTARRED QUESTION NO.3246 TO BE ANSWERED IN THE LOK SABHA ON 14.08.2003.

Major Hydro Projects proposed for development in N.E. Region
Sl.No.	Name of Schemes / State / Executing Agency	I.C. (MW)
1. Kameng, Arunachal Pradesh, NEEPCO 4 x 150 =600

2. Subansiri Lower, Arunachal Pradesh, NHPC 8 x 250 =2000

3. Subansiri Middle, Arunachal Pradesh, NHPC 8 x 200 =1600

4. Subansiri Upper, Arunachal Pradesh, NHPC 8 x 250 = 2000

5. Siang Middle, Arunachal Pradesh, NHPC 4 x 250 =1000 6. Siang Upper, Arunachal Pradesh, NHPC 11000

7 Ranganadi Stage-II, Arunachal Pradesh, NEEPCO 2 x 65 = 130

8. Dikrong, Arunachal Pradesh, NEEPCO 2 x 50 =100

9. Kopili H.E. Project - Stage-II, Assam, NEEPCO 25 10. Lower Kopili, Assam, NEEPCO 3 x 50 =150 11. Hirit, Arunachal Pradesh, NEEPCO 50 12. Papumpam, Arunachal Pradesh, NEEPCO 60 13. Tipaimukh, Manipur, NEEPCO 1500 14. Tuivai, Mizoram, NEEPCO 3 x 70 =210 15. Bairabi, Mizoram, Govt. of Mizoram 2 x 40 = 80 16. Tuirial H.E. Project, Mizoram, NEEPCO 60 17. Tripura Gas based Power Project, Tripura, NEEPCO 280
Total = 20845