Question : CONSTRUCTION OF FISH LANDING CENTRES



(a) whether the Union Government have received a proposal from some States for sanction and release of Central assistance for construction of fish landing centres particularly at Kodibengre in Karnataka;

(b) if so, the details thereof, State-wise and location-wise; and

(c) the status of these proposals?

Answer given by the minister

THE MINISTER OF STATE IN THE MINISTRY OF AGRICULTURE (SHRI HUKUMDEO NARAYAN YADAV)

(A), (B) & (C) Yes, Sir.

A STATEMENT SHOWING DETAILS OF ONGOING PROJECTS IN VARIOUS COASTAL STATES, LOCATION- WISE APPROVED BY THE UNION GOVERNMENT UNDER THE CENTRALLY SPONSORED SCHEME FOR CONSTRUCTION OF FISH LANDING CENTRES, INCLUDING KODIBENGRE IN KARNATAKA, IS ANNEXED.

Annexure

STATEMENT REFERRED TO IN REPLY TO THE LOK SABHA UNSTARRED QUESTION NO. 5363 PUT IN BY SHRI C. SREENIVASAN AND SHRI G. PUTTA SWAMY GOWDA FOR ANSWER ON 28.04.2003 REGARDING CONSTRUCTION OF FISH LANDING CENTRES.

(Rs. in Lakhs)
S.No. Name of States with Appr- Funds Status of the proposals location of Fish oved Released landing Centre, Cost against approved under the 50% central CSS with 50% financial assistance assistance
(I) ANDHRA PRADESH
1. Mangipudi FLC 17.00 2.10 State Govt has been requested to furnish latest progress report

2. Baruva FLC 83.60 22.00 Approved in March 2003.State Govt. is yet to commence construction work.

3. Perupalem FLC 88.86 24.00 -do-

4. Gondisamudram FLC 88.86 23.90 -do-

5. Isakapallipattapupalem 85.62 23.00 -do- FLC 6. Thatichetlapalem FLC 84.86 23.00 -do-

7 Navvalarevu FLC 79.35 23.00 -do-

8. Bandaruvanipeta FLC 79.00 23.00 -do-

9. Chintapalli FLC 79.77 23.20 -do- 10. Pudimadaka FLC 78.00 22.60 -do- 11. Mukkam FLC 79.77 23.20 -do- 12. Mypadu FLC 81.16 23.525 -do-
(II). KARNTAKA

1. Alvekodi FLC 89.53 10.00 Only 4% of the project work completed.

2. Belikeri FLC 67.40 25.00 Project work not yet commenced by the States due to modification in the approved proposal by them.

3. Hejomodikodi FLC 95.00 47.50 90% project work completed.

4. Kodibengre FLC 55.50 27.75 Jetty opened on 1.10.2000.
(III) ORISSA

1. Kirtania FLC 172.00 86.00 Project nearing completion.

2. Penthakata FLC 80.20 5.00 Project work yet to be taken up for construction by the State.

3. Talasari FLC 162.10 81.05 Project nearing completion.

4. Gopalpur on Sea FLC 96.00 48.00 Construction of landing platform, auction hall, net mending shed, pavement & approach road completed.

5. Hata Baradi FLC 62.00 16.00 Progress report has not received from State 6. Nairi Stage-III FLC 38.86 15.00 Progress report has not received from State

7 Balugaon FLC 235.50 57.75 Approved in March 2003.State Govt. is yet to commence construction work.

(IV) MAHARASHTRA
1. Sarjekota 30.00 - Not yet taken up for construction by the State.

2. Alibagh Koliwada FLC 32.53 16.265 90% of the project work completed.

3. Ekdara Koliwada FLC 38.66 19.33 Work completed. The State is yet to submit completion report

4. Tarkarli FLC 53.34 26.67 -do-

5. Achara Peerwada 55.16 27.58 Work in progress. 6. Taramumbri FLC 97.02 48.51 Work completed. The State is yet to submit completion report

7 Rajpuri Koliwada 73.96 36.98 -do-
(V) GUJARAT
1. Navabundar FLC 163.30 55.00 Environmental clearance for implementation of the project is being obtained by the State.

2. Dhamlej FLC 31.00 8.00 Work in progress
Kerala

1. MoylaliKaddapuram FLC 85.20 42.60 Major items of the project are completed.

2. Kanhangad FLC 28.42 2.50 Not yet commenced the construction works by the State.

3. Thikkodi FRLC 49.25 24.625 Major items of the project Work completed.

4. Poovar FLC 26.99 2.50 Not yet commenced the construction works by the State..

5. Kadapra FLC 18.52 9.26 Work in progress. 6. Kattor PollathaiFLC 50.25 25.125 Work completed. The State is yet to submit completion report.
TAMIL NADU

1. Arcocuttothurai 132.32 35.00 Not yet taken up for construction by the State.

2. Veerapandiapattinam 132.32 35.00 -do-

3. Pulicat 132.32 66.16 70% of the project work completed.

4. Punnakayal 132.32 66.16 80% of the project work completed.

5. Thengapattinam 132.32 35.00 Not yet taken up for construction by the State 6 Mudasalodai 132.32 66.16 80% of the project work completed.

7 Pamban 132.32 35.00 Not yet taken up for construction by the State.

8. Jagathapattinam 132.32 66.16 80% of the project work completed.

9. Nagapattinam 132.32 35.00 Not yet commenced the construction works by the State. 10. Sethuapavastram 132.32 66.16 70% of the project work completed.
GOA

1. Malim FLC 89.25 44.625 Work in progress.

2. Cutbona FLC 89.20 44.60 70% of the project work completed.

3. Cortalim FLC 89.31 44.655 85% of the project work completed.