Question : New Rail Lines from Anupgarh to Bikaner

(a) whether the Government has conducted any survey for laying new railway line from Anupgarh (Sriganganagar) to Bikaner of Rajasthan;

(b) if so, the details thereof;

(c) whether the Government proposes to start work on this route in near future;

(d) if so, the details thereof; and

(e) if not, the reasons therefor?

Answer given by the minister

MINISTER OF STATE IN THE MINISTRY OF RAILWAYS

(SHRI RAJEN GOHAIN)

(a) to (e) Yes, Madam. As per survey report, the cost of project of 154.437 km new line was `972.92 crore with negative rate of return of 6.42%. The project could not be taken forward as it was financially not viable, poor traffic potential and Railways has already got a large shelf on ongoing projects.

*****