THE MINISTER OF WATER RESOURCES(PROF. SAIF-UD-DIN SOZ)
(a)to(e) A Statement is laid on the Table of the House.
STATEMENT REFERRED TO IN REPLY TO LOK SABHA STARRED QUESTION NO.63 REGARDING PENDING IRRIGATION PROJECTS FOR REPLY ON
03.03.2008.
(a) So far Central Assistance under AIBP has been provided to 236 major and medium projects/project components. Of these,
177 projects were taken up under AIBP during 9th and 10th Plan. So far, 91 projects/project components have been completed
which includes 61 projects of 9th and 10th Plan.
(b) Project wise and statewise details are enclosed.
(c) As per existing procedure, all the major and medium projects under AIBP are monitored by the Central Water Commission
by paying field visits twice a year which is to be followed up by the submission of Monitoring Report to the Ministry of
Water Resources and other concerned offices including Water Resources/Irrigation Department of the State Governments.
Periodic Reviews have also being taken from time to time by the Ministry of Water Resources with the State Governments.
(d) On the basis of reviews and monitoring done from time to time, the Ministry of Water Resources has initiated several
measures to expedite completion of ongoing irrigation projects under AIBP which includes vigorous monitoring of the projects,
linking utilization of Central Assistance to physical achievements in terms of potential creation, release of grants based
on Memorandum of Understanding and Utilization Certificates, taking up new projects only against completion of one ongoing
project etc. These measures have resulted in record potential creation under AIBP of 9.37 lakh ha during 2006-07.
The projects to be included in AIBP in the Eleventh Plan are ongoing projects under AIBP spilling over from tenth plan,
ongoing and new projects of the Prime Minister`s Relief Package for agrarian distress districts, projects benefiting
drought prone/tribal areas, projects benefiting States having irrigation development below National Average and new
projects based on 1:1 criteria.
(e) A Statement indicating state wise names of the ongoing AIBP projects, year of inclusion in AIBP, present status of
completion, anticipated date of completion, Central Assistance provided during 2004-05 up to 27th February 2008, targeted
potential under AIBP and potential created up to March 2007 is given in the enclosed statement.