MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI R. VELU )
(a) to (e) : A statement is attached.
STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (e) OF THE
UNSTARRED QUESTION NO. 674 BY SHRI RAMSEVAK SINGH TO BE
ANSWERED IN LOK SABHA ON 28.07.2005 REGARDING GUNA-ETAWAH
RAIL LINE PROJECT.
(a) to (d): The work of construction of new broad gauge
rail line between Guna and Etawah (344 kms.) was included
in the Budget 1985-86. Guna to Bhind (306 kms.) has
since been completed and opened to traffic in the following
three phases:-
Section Commissioned on
Guna-Shivpuri (102 kms.) Feb,1991 Shivpuri-Gwalior (125 kms.) April,1999 Gwalior-Bhind (79 KMS.) July,2002
In the last leg of the project between Bhind and Etawah (38
kms.), 79% of the work has been completed. On this
section, land in wildlife sanctuary area still remains to
be handed over. The completion of work of this section
would depend upon handing over of the land to the Railways.
(e) : An outlay of Rs. 25 crore has been provided for
this project during the current financial year.