(a) whether the work on doubling of railway track between Barasat-Hasnabad section is going at a
very slow pace;
(b) if so, the status of the project; and
(c) the time frame by which the project would be completed?
(a) whether the work on doubling of railway track between Barasat-Hasnabad section is going at a
very slow pace;
(b) if so, the status of the project; and
(c) the time frame by which the project would be completed?
MINISTER OF STATE IN THE MINISTRY OF RAILWAYS(DR. R. VELU )
(a) to (c) : The work was targeted for completion during 2008-09 but will spill over to 2009-10
due to delay in land acquisition, contract failure and abnormally heavy rain.The progress of
project is about 50% and is targeted for completion during 2009-10.