(a) the present status of surveys/ projects going on in Madhya
Pradesh;
(b) the progress made in regard to these surveys/projects; and
(c) the time by which these projects/surveys are likely to be
completed?
(a) the present status of surveys/ projects going on in Madhya
Pradesh;
(b) the progress made in regard to these surveys/projects; and
(c) the time by which these projects/surveys are likely to be
completed?
MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI R. VELU)
(a) to (c): A Statement is attached.
STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (c) OF THE UNSTARRED
QUESTION NO. 335 ASKED BY SHRI SHIVRAJ SINGH CHOUHAN TO BE ANSWERED
IN THE LOK SABHA ON 24.11.2005 REGARDING RAILWAY PROJECTS IN M. P.
(a) to (c): The project-wise progress along with the target dates
of completion, wherever fixed and budget allocation during 2005â06
for various ongoing New Line, Gauge Conversion and Doubling
projects in Madhya Pradesh are as given under:-
S. Name of the Anticipa- Budget Present Status No Project ted Cost allocation (Rs. in during crore) 2005â06 (Rs. in crore)
New Line 1. GunaâEtawah 423.00 25.00 GunaâBhind (308 Kms) via completed and commissioned. ShivpuriâGwa 77% progress in earthwork, liorâBhind bridgeworks and ballast (348.25 Kms) supply in progress on BhindâEtawa (36 Kms).
2. LalitpurâSat 925.00 25.00 Work being taken up in na, phases. Final Location RewaâSingrau Survey for li & LalitpurâKhajuraho (167.5 MahobaâKhaju Kms) & MahobaâKhajuraho (65 raho Kms) completed. FLS for (541 Kms) KhajurahoâSatna (116 Kms) & RewaâSingrauli (191.6 Kms) is in progress. Earthwork & bridgeworks taken up in the entire length, where land has been made available.
3. GodhraâIndor 946.16 15.00 DewasâMaksi (36 Kms) e via Dahod, completed and commissioned. Sardarpur, Dhar & DewasâMaksi (316 Kms)
4. Ramganj 726.05 15.00 In Ramganj MandiâJhalawar MandiâBhopal 10.88 hectare land (262 Kms) acquired. Tenders processed for earthwork & minor bridges for initial 27 kms., i.e. from Ramganj Mandi to Jhalawar.
Gauge Conversion 5. JabalpurâGon 511.86 25.00 GondiaâBalaghat section dia incl. completed and commissioned. BalaghatâKat On JabalpurâBalaghat angi section land acquisition (285 Kms) taken up. Earthwork and bridgeworks taken up on GwarighatâKachhepura stretch and BalaghatâKatangi sections. Over all progress 17.4%.
6. NeemuchâRatl 167.51 20.00 Earthwork & bridgeworks and am ballasting taken up. Over (135.38 Kms) all physical progress 90%.
Doublings 7 Akodia- 31.36 12.12 Yard Plan for 3 stations Sujalpur and all âLâ section drawing approved. Tenders for earthwork, minor bridges and ballast supply invited. 8. Kalapipal- 97.64 25.00 During the current Phanda/Maksi- financial year, two block Bhopal sections i.e. Sehore- Panchawan and Panchawan- Phanda targeted for completion. Overall progress 36%.