Question : EXPANSION OF NLC



(a) whether there is any proposal for further expansion of the Neyveli Lignite Corporation (NLC) in Tamil Nadu;

(b) if so, the details thereof;

(c) the funds earmarked for the purpose; and

(d) the time by which it is likely to be completed?

Answer given by the minister


MINISTER OF STATE FOR COAL (SHRI PRATIK PRAKASHBAPU PATIL)

(a): Yes, Sir.

(b): Neyveli Lignite Corporation (NLC) has taken up the following Thermal Power Projects approved by the Government of India for further expansion in the State of Tamil Nadu.

1. Thermal Power Station TPS-II Expansion at Neyveli (2 x 500 MW)

2. NTPL – Coal based Power Station at Tuticorin (2 x 500 MW).

3. New Neyveli Thermal Power Station at Neyveli (2 x 500 MW), which are under implementation.

(c) : The Estimated Project Cost for these projects are –

S.No.	Project	Project cost	in Crores 
1. TPS-II Expansion at Neyveli 2453.57
2. NTPL at Tuticorin 4909.54
3. New Neyveli Thermal Power 5907.11 Station at Neyveli

(d) : The time by which these projects are likely to be completed is tabulated below :
S.No.	Project	Time Schedule

1. TPS-II Expansion at Neyveli Unit-I-December, 2011 & Unit-II-July, 2012

2. NTPL at Tuticorin Unit-I-February, 2013 & Unit-II-January, 2013

3. New Neyveli Thermal Power Station Unit-I-June’2015 & Unit-II-December, 2015