MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI ADHIR RANJAN CHOWDHURY)
(a) to (e): A statement is laid on the Table of the House.
STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (e) OF UNSTARRED QUESTION NO. 4928 BY SHRI
BHARTRUHARI MAHTAB, SHRI RUDRA MADHAB RAY, SHRI KALILKESH N. SINGH DEO, AND SHRI AMARNATH
PRADHAN TO BE ANSWERED IN LOK SABHA ON 25.04.2013 REGARDING RAILWAY NETWORK IN ODISHA.
(a): Railway Projects announced during the last Five Year Plan (2007 â 2012)
S.No. Name of Project Year of Amount Latest Expen- Present inclu-sion allo- Antici diture Status in the cated in -pated upto Budget 2013-14 cost March, (in Crore) (in 2013 Crore) (in Crore)
1 Raipur-Titlagarh 2007-08 96.91 614.35 51.42 Detailed (203 Km) (doubling) Estimate including New Line sanctioned Mandir Hasaud Naya and Raipur(20Km) & new earthwork MM for conversion & ballast of Raipur (Kendri) supply -Dhamtari & commenced. Abhanpur- Detailed Rajimbranch Estimate (67.20Km) also sanctioned for Mandir Hasaud Naya Raipur Section.
2 Rupsa- (1995-96) 0.84 643.97 173.04 Rupsa Bangriposi(90Km) 2007-08 Bangriposi (GC) with Completed Buramara- and Chakulia commis (50Km-Newline) sioned. Buramara -Chakulia work entrusted to RVNL on SPV mode and Banka bility study taken up.
3 Barbil- 2007-08 2.00 56.00 50.18 Completed Barajamda and (10Km) commissi (doubling) oned.
4 Dumetra- 2007-08 120.00 94.77 Completed Champajharan. and (19Km) commissi (doubling) oned.
5 Banspani- 2008-09 1.00 90.88 55.90 Section Jaroli (8.7Km) commissi (doubling) oned.
6 Banspani- 2009-10 90.37 942.45 80.88 3 contracts Daitari- awarded, Tomka- earthwork Jakhapura & Bridges (180 Km) taken up. (doubling)
7 Brundamal- 2009-10 01.00 81.66 3.00 Detailed Jharsuguda- Estimate Flyover under connection sanction. for joining DN Line.
8 Sambalpur- 2010-11 50.00 679.27 36.00 Final Talcher Location (174.11 Km) Survey (doubling) completed & estimate taken up.
9 Delang-Puri 2010-11 55.00 165.16 33.30 Detailed (28.7 Km) Estimate (doubling) sanctioned. Contract for Earthwork & bridges awarded and work taken up. Delang- Sakhigopal section targeted for 2013-14.
10 Champajharan 2010-11 20.00 177.38 24.36 Contract -Bimlagarh for ballast (21km) and earth (doubling) work awarded and work taken up.
11 Digha-Jaleswar 2010-11 1.00 352.65 4.20 Detailed (41Km) Estimate (New Line) sanctioned. Land acquisition taken up.
12 Simhachalam 2011-12 10.00 23.33 10.00 Track North linking Gopalapatnam completed. â doubling of byepass line (2.07Km)
13 Kirandul- 2011-12 142.50 826.57 01.00 MoU signed Jagdalpur with NMDC (150Km) Ltd. Part- (doubling) Detailed Estimate has been sanctioned for 327.96 Cr. (for 0 to 45. 5 Km.)
14 Khurda Road 1994-95 60.00 1995.25 244.41 86% of -Bolangir physical (289 Km) work in (new Line) respect of Phase-I (from Khurda Road to Begunia) of Khurda Road â Bolangir New Line Project has been completed. Khurda Road â Khurda Town Section has been completed in 2012-13. Khurda Town â Sunakhela section falling on Khurda Road â Nayagarh is targeted for completion in 2013-14.
(b): Orissa is having a network density of 6.69 Km. per lakh of population which is higher
than National average of 6.22 Km per lakh of population. In area terms, network density of
Orissa is 15.81 Km per 1000 Sq.Km which is less than national average of 19.61 Km.
(c) to (e): Yes Madam. Letters from public representatives from Odisha including Shri Kalikesh
N. Singh Deo, MP, Shri Rama Chandra Khuntia, MP, and Shri Naveen Patnaik, Chief Minister of
Odisha regarding improvement of rail connectivity in Odisha were received and the same were
acknowledged/replied after due examination.
7 New Line projects covering a length of 906.7Km and 16 Doubling/GC projects covering a length
of 1354 Km falling fully/partly in Orissa have been taken up. On completion, these projects
will augment Railway network in Orissa.