(a) the details of the gauge conversion projects being
undertaken at present in North Eastern Railways, Gorakhpur;
(b) the progress made so far on each project; and
(c) the time by which these projects are likely to be
completed ?
(a) the details of the gauge conversion projects being
undertaken at present in North Eastern Railways, Gorakhpur;
(b) the progress made so far on each project; and
(c) the time by which these projects are likely to be
completed ?
MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI R. VELU)
(a) to (c): A statement is attached.
STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (c) OF THE
UNSTARRED QUESTION NO. 2405 ASKED BY SHRI YOGI ADITYA NATH TO BE
ANSWERED IN LOK SABHA ON 08.12.2005 REGARDING GAUGE CONVERSION
PROJECTS.
(a) to (c): The details of ongoing Gauge Conversion projects
under North Eastern Railway indicating the anticipated cost,
expenditure incurred upto March, 2005, outlay provided during
2005-06 and status alongwith target date for completion wherever
fixed is as under :-
(Rs. in Crore)
S. Name of the Anti Expend- Outlay Status along with No. Project ci- iture 2005- target date for pated upto 06 completion Cost March, wherever fixed 2005
1. Kaptanganj - 320.10 31.09 18.00 The overall Thawe-Siwan - physical progress Chhapra is about 33%. (233.50 Kms) Earthwork and bridge works etc. have been taken up. Out of this, Thawe-Siwan Section is targeted for opening during 2005-06.
2. Kanpur-Kasganj- 661.72 207.25 43.35 The overall Mathura -Bareilly physical progress including is 42%. Kanpur- material Farrukhabad modification for section is extension from targeted for Bareilly to completion during Lalkuan on Kanpur- 2005-06. Farrukhabad section (544.5 Kms).
3. Gonda-Bahraich- 73.42 2.27 0.01 The overall Sitapur-Lucknow physical progress Ph-I is 5%. Earthwork (479.9 Kms) and bridges taken up.
4. Gonda-Gorakhpur 381.17 44.11 0.10 The overall Loop with physical progress Anandnagar- is 13%. Earthwork Nautanwa and bridges taken (260 Kms) up.
5. Aunrihar-Jaunpur 85.92 0.02 2.00 Earthwork & minor (50.60 Kms) bridges taken up.