Question : SURVEY OF RAIL LINE IN CHHATTISGARH



(a) whether the Railways have received any request to include Mungeli and Uslapur section in the ongoing survey being carried out for rail line in the Dongargarh-Kota section of Chhattisgarh;

(b) if so, the details thereof;

(c) the status of the survey carried out in this regard; and

(d) the time by which survey report is likely to be submitted?

Answer given by the minister


MINISTER OF STATE IN THE MINISTRY OF RAILWAYS(SHRI K.H. MUNIYAPPA)

(a) & (b): South East Central Railway has received a request in this regard to include Mungeli and Uslapur in the ongoing survey.

(c) & (d): The survey for the new line is being done as per the original alignment between Dongargarh – Kota which is not passing via Mungeli and Uslapur.Field Survey for 90 Km out of approximately 220 Km has been completed.The survey report is likely to be available by 15.04.2010.