Question : ROB RUB SANCTIONED ON HAJIPUR-MUZAFFARPUR LINE



(a) the details of over bridges/under bridges sanctioned on Hajipur-Muzaffarpur and Muzaffarpur-Samastipur rail line, location-wise;

(b) the time by which work is likely to be started and completed; and

(c) the details of expenditure likely to be incurred thereon?

Answer given by the minister

MINISTER OF STATE IN THE MINISTRY OF RAILWAYS ( SHRI BANDARU DATTATRAYA )

(a): Four works of Road over bridges have been sanctioned.

Two on Muzaffarpur-Samastipur line i.e. in lieu of Level Crossing (LC) No. 101 & 101/A between Narainpura-anant & Muzaffarpur.

Two on Hajipur-Muzaffarpur line in lieu of LCs No. 47 & 54/A between Hajipur & Sarai Stations.

(b): Road over/under bridge is constructed jointly by Railway and State Govt. Railway construct Bridge proper (over the track) and approaches are built by State Govt. Efforts are made by Railway to complete its portion before or alongwith approaches by State Govt.

(c): Estimated cost of works is as under:-

1. ROB at LC No. 47	-	Rs. 11.35 cr. 

2. ROB at LC No. 54/A - Rs. 11.58 cr.

3. ROB at LC No. 101 - Rs.11.47 cr.

4. ROB at LC No. 101/A - Rs.12.55 cr.