THE MINISTER OF STATE IN THE MINISTRY OF SHIPPING, ROAD TRANSPORT AND HIGHWAYS (SHRI K. H. MUNIYAPPA)
(a) to (d) The construction of access controlled 6/8 laning of Delhi âGurgaon Section of NH-8 on Build Operate and Transfer (BOT) basis has been delayed due to change in scope of work and delay in acquisition of Government land. An increase of Rs. 155 crores in cost of project has been assessed due to change in scope of work.
(e) The construction of Delhi â Gurgaon Section of NH-8 as originally planned is likely to be completed by December, 2006. The additional works especially RTR â Palam flyover is likely to be completed by June, 2007.
Detailed Project Report for construction of 135 km long Eastern Peripheral Expressway (Kundli- Ghaziabad â Noida- Palwal; NH- NE -2 ) is under preparation. The project is scheduled to start in October, 2007 and to complete in October, 2010.
Other expressway projects are at planning stage only. Approximately 1000 km of expressways will be taken up under NHDP Phase âVI over the next few years and will be completed by 2015 -16.