Question : ELECTRIFICATION OF RAILWAY ROUTES



(a) The length of railway track electrified as on date, zone-wise State-wise;

(b) The details of the routes on which the electrification work is going on at present alongwith the target date for its completion, Zone/State-wise;

(c) whether the Government have reviewed the progress of on-going electrification of rail routes;

(d) if so, the finding thereof and the steps taken by the Government in this regard;

(e) The total length of railway track to be electrified during the Ninth Five Year Plan, Zone/State-wise, and

(f) the achievement made so far in this regard, Zone/State-wise?

Answer given by the minister

MINISTER OF STATE IN THE MINISTRY OF RAILWAYS ( SHRI DIGVIJAY SINGH )


(a) to (f) : A Statement is attached.

Statement referred to in reply to Unstarred Question No.113 by S/Shri Manoj Sinha, Brijlal Khabri, Ananta Nayak, Annasaheb M.K. Patil, Haribhau Shankar Mahale, Abdul Rashid Shaheen, to be answered in Lok Sabha on 24.2.2000 regarding Electrification of Railway Routes.


(a) As on 31.3.1999, 14,579 Route Kilometres have been electrified. Zone-wise and State-wise details as under: -

ZONE-WISE DETAILS OF ELECTRIFICATION

Sr. No.	Zone	Route Kilometres Electrified
1 CENTRAL 2947 2 EASTERN 2053 3 NORTHERN 1387 4 SOUTHERN 1266 5 SOUTH EASTERN 3615 6 SOUTH CENTRAL 1518 7 WESTERN 1793 8 NORTH EASTERN 0 9 NORTH EAST 0 FRONTIER

TOTAL 14579

STATE-WISE DETAILS OF ELECTRIFICATION

Sr. No. STATE Route KilometresElectrified

1 Andhra Pradesh 1940 2 Bihar 1800 3 Delhi 129 4 Gujarat 651 5 Haryana 341 6 Karnataka 104 7 Kerala 164 8 Madhya Pradesh 2741 9 Maharashtra 1821 10 Orissa 551 11 Punjab 159 12 Rajasthan 491 13 Tamil Nadu 836 14 Uttar Pradesh 1219 15 West Bengal 1632 16 Other States 0
TOTAL 14579



(b): The details of the routes on which the Electrification work is going on at present is given State-wise/Zone-wise as under:

S.No.	Routes	State	Zone	Target
1. Erode-Ernakulam Tamil Nadu/Kerala SouthernMarch 2000

2. Adra-Midnapur West Bengal South Eastern March 2000

3. Lucknow-Kanpur Uttar Pradesh Northern March 2000

4. Sitarampur-Mughalsarai West Bengal/Bihar Eastern March 2002+ /Uttar Pradesh

5. Delhi-Ambala-Ludhiana Delhi/Haryana/Punjab Northern March 2001 incl. Ambala-Kalka & Sirhind-Nangal Dam 6. Bokaro-Barsuan Bihar/Orissa/ South Eastern March 2002+ West Bengal
7. Kusunda-Jamuniatand Bihar Eastern March 2001

8. Kharagpur-Bhubaneswar West Bengal/Orissa South Eastern March 2003+

9. Bhubaneswar-Kottavalasa Orissa/Andhra Pradesh South Eastern March 2003+ 10. Udhna-Jalgaon Gujarat/Maharashtra Western March 2003+ 11. Ambala-Saharanpur Haryana/Uttar Pradesh Northern March 2003+ -Moradabad
12. Tambaram-Chengalpattu Tamil Nadu Southern March 2004+ - Villupuram & Chengalpattu-Arakkonam
13. Ludhiana-Amritsar Punjab Northern March 2004+ 14. Renigunta-Hospet Karnataka/Andhra Pradesh South Central March 2006+

+ Tentative targets subject to availability of resources.

(c) & (d). Yes, Sir. The progress of electrification projects is monitored periodically. Requisite inputs are provided wherever required.
(e) & (f). The route kilometers to be electrified during the Ninth Five Year Plan and the achievements during the First Two years of the Ninth Plan are indicated Zone-wise & State-wise in the tables below:

Zone-wise Target/Achievements
S.No. Zonal Railway Target/Achievement for Target Electrification(Route Kilometres) during Ninth Five Year Plan Target Achievement till 31.3.1999

1 Northern 301 118 2 South-Eastern 1250 637 3 Southern 141 81 4 Western 83 - 5 Eastern 521 222 6 South-Central 4 4
TOTAL 2300 1062

State-wise Target/Achievements

S.No. state Target/Achievement for Target Electrification(Route Kilometres) during Ninth Five Year Plan Target Achievement till 31.3.1999
1 Andhra Pradesh 231 181 2 Bihar 717 309 3 Gujarat 68 - 4 Haryana 41 41 5 Kerala 107 77 6 Maharashtra 15 Nil 7 Orissa 450 112 8 Punjab 148 41 9 Tamil Nadu 34 4 10 Uttar Pradesh 166 34 11 West Bengal 323 263
TOTAL 2300 1062