THE MINISTER OF STATE IN THE MINISTRY OF POWER (SHRI K.C. VENUGOPAL)
(a) & (b): Under Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), 576
phase-I projects covering electrification of 1,18,499 un/de-electrified villages
have been sanctioned including tribal dominated villages in the country
including Madhya Pradesh. Cumulatively, as on 15.07.2011, the electrification
works in 98,174 un/de-electrified villages have been completed under RGGVY.
The coverage and achievement of electrification of un/de-electrified villages
for the sanctioned projects under RGGVY, State-wise, is at Annex-I. 16
projects of M.P. were not sanctioned in Phase-I, being high cost projects,
relative to benchmark costs of electrification. These projects are part of
Phase-II RGGVY projects and after recent approval from Planning Commission
for same of Phase-II projects are under active consideration.
(c): There is no upfront allocation of funds for any
State/district/village under RGGVY. Funds are released against sanctioned
projects in instalments based on the reported utilization of amount of the
previous instalment(s) and fulfillment of other conditionalities. The details of
release of funds for the sanctioned projects under RGGVY during the last
three years and current year, State-wise, is at Annex-II.
(d) & (e): Ministry of Power and Rural Electrification Corporation Limited,
the nodal agency for RGGVY, is regularly conducting review meetings to
monitor the progress of RGGVY works under implementation. Further, REC is
also interacting with the all State Governments and respective implementing
agencies at the highest level to expedite the RGGVY works. To ensure
qualitative execution of rural electrification works, a three tier quality control
mechanism has been enforced under RGGVY in 11th Plan. Web based
milestone monitoring mechanism is also in place.
(f): The electrification works for the sanctioned projects including
tribal villages under the sanctioned projects are expected to be completed by
the end of 11th Plan period.