THE MINISTER OF STATE IN THE MINISTRY OF COAL AND MINISTER OF STATE IN THE MINISTRY OF MINES
(DR. DASARI NARAYAN RAO):
(a) to (d) As reported by Goal India Limited, rehabilitation of project affected people is a continuous process in which rehabilitation of displaced families is done in phases in accordance CIL`s Resettlement and Rehabilitation (R&R) Policy, 2000. The subsidiary companies make all efforts to settle the cases within the minimum possible time and start mining operations only after affected persons are rehabilitated. As per records available, company-wise cases settled as on 1st March, 2005 are as under:
Sl.No. Name of the Company No. of families No. of families displaced rehabilitated
1. Eastern Coalfields Ltd. 1593 1593
2 Bharat Coking Coal Ltd. 1573 1573
3. Central Coalfields Ltd. 1666 1666
4. Western Coalfields Ltd. 5503 5503
5. South Eastern Coalfields Ltd. 4281 4281
6. Mahanadi Coalfields Ltd. 2576 2576
7 Northern Coalfields Ltd. 2321 2321
8. North East Coalfields Ltd. Nil Nil Total: 19,513 19,513