Question : Wardha-Nanded Railway Line

(a) the steps taken by the Government to connect Wardha-Yavatmal-Nanded railway line with Nagpur-Goa railway line;

(b) whether Wardha-Yavatmal-Nanded railway line is being constructed in phases;

(c) if so, the reasons therefor;

(d) the funds allocated by the Government so far for completing this work speedily and the time by which the construction of missing link is likely to be completed; and

(e) the time by which the construction work of above-said line is likely to be completed and whether any time-limit has been fixed in this regard and if so, the details thereof?

Answer given by the minister

MINISTER OF STATE IN THE MINISTRY OF RAILWAYS

(SHRI RAJEN GOHAIN)


(a) to (e): Wardha-Nanded via Yavatmal-Pusad (284 km) new line project has been taken up on cost sharing basis with Government of Maharashtra (Railways 60% & GoM 40%). Latest anticipated cost of the project is `3169 crore. An expenditure of `714.72 crore has been incurred upto March, 2018 and an outlay of `379 crore has been provided in 2018-19.

The project is being constructed in two phases as the project is lengthy: (i) Wardha to Yavatmal (78 km) and (ii) Yavatmal to Nanded (206 km).

Earthwork and work of major bridges / minor bridges / RUBs have been taken up in Wardha-Kalamb section of Phase-I.

Target date of completion can be fixed only after complete land acquisition. 694.08 Ha. land has been acquired out of 1678.48 Ha.

*****