Question : Irregularities in Bharatnet project

(a) whether the Government is lagging behind in achieving the targets of connecting Gram Panchayats by Broadband under the Bharatnet Project in the country;

(b) if so, the details thereof, State-wise and the reasons therefor; and

(c) the number of complaints received by the Government regarding irregularities in implementation of the Bharatnet Project across the country along with action taken/ being taken by the Government on such complaints so far, State-wise?

Answer given by the minister

MINISTER OF COMMUNICATIONS, LAW & JUSTICE AND
ELECTRONICS AND INFORMATION TECHNOLOGY
(SHRI RAVI SHANKAR PRASAD)

(a) & (b) BharatNet project is being implemented in a phased manner to provide broadband connectivity to all the Gram Panchayats (approx. 2,50,000) in the country. In December 2017, the phase-I of the BharatNet project was completed by connecting one lakh Gram Panchayats (GPs). A modified strategy to implement BharatNet has been approved by Cabinet on 19.07.2017, which provides an optimal mix of media to connect GPs, implementation by State-led Model, Private Sector, and Central Public Sector Undertaking (CPSU) Model; laying of fresh fibre from Block to GPs and setting up of last mile architecture at all GPs. As on 04.07.2019, a total of 1,21,416 GPs (including Block Headquarters) have been made Service Ready. The State-wise status of BharatNet is attached at Annexure-I.

The delay in the initial implementation of the project was on account of:

(i) Delay in the initial commencement of project as the work on the project began in the second half of 2014 due to field survey of GPs and pilot testing of the technology model.
(ii) Only one media that is underground Optical Fibre Cable (OFC) to cover GPs, and Right of Way (RoW) issues.

Since May 2016, with the constitution of the following committees, the issues are being resolved timely:

i) Empowered Committee under Secretary, Department of Telecommunications (DoT)
ii) Steering Committee under Administrator, Universal Service Obligation Fund (USOF).
iii) State Committee under Chief General Manager (CGM), Bharat Sanchar Nigam Limited (BSNL) for resolution of State level issues.

(c) As per the information provided by the Vigilance Wing of Department of Telecommunications (DoT), and Bharat Broadband Network Limited (BBNL), the details are given in Annexure-II.