Question : LOWER SUBANSIRI HYDRO ELECTRIC PROJECT



(a) whether the Government is considering to review the construction of Lower Subansiri Hydro Electric Project in Arunachal Pradesh;

(b) if so, the details thereof;

(c) the present status of its construction and the progress made in this regard so far;

(d) whether the Government proposes to re-design the dam in view of the recent havoc caused by the cloud burst in Uttarakhand and widespread protests of the people of Assam due to dangers of the dam; and

(e) if so, the details thereof?

Answer given by the minister


THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER ( SHRI JYOTIRADITYA M. SCINDIA )

(a) : No, Madam.

(b) : Does not arise.

(c) : The works of the Project are at a stand still since 16.12.2011 due to agitation/protest by various organisations of Assam. The progress made so far is at Annex.

(d) & (e) : The Government has, inter-alia, directed NHPC to make necessary changes in some of the features of the dam etc., as recommended by the Dam Design Review Panel constituted for the purpose.