THE MINISTER OF STATE IN THE MINISTRY OF POWER (SHRI K.C. VENUGOPAL)
(a)to(c): The State-wise and utility-wise details of actual hydro
generation vis-Ã -vis target from Hydro Stations (above 25 MW) during 11th
Five Year Plan (2007-08 to 2011-12 upto Nov.,2011) is at Annex-I.
During 2008-09 & 2009-10, the generation has been less than
the targets by 4.35% and 9.90% respectively. However, during 2010-11, the
generation was higher than the targets by 3.06%. The power generation
during 2008-09, 2009-10 was less as compared to target fixed due to less
availability of water for power generation because of less rain fall.
Working Group on power has been constituted by the Planning
Commission to formulate the 12th Five Year Plan for the Power Sector which will
include capacity addition target, fund requirement etc. for the 12th Five Year
Plan.
(d) & (e) : Details of various hydro-electric projects (25 MW & above) under
construction in the country as per 11th Plan programme along with
commissioning schedule original/latest, issues/constraints for delay etc. is
atAnnex-II. To ensure that the hydro projects under construction are
completed within the stipulated time, following mechanism is in place:
# Central Electricity Authority (CEA) is performing the duties of monitoring
of the power projects in pursuance of 73 (f) of Electricity Act, 2003. The
progress of each project is monitored continuously through frequent site
visits, interaction with the developers, critical study of monthly progress
reports. Chairperson, CEA holds review meeting with the developers and
other stakeholders to sort out the critical issues.
# A Power Project Monitoring Panel (PPMP) has been set up by the Ministry
of Power to independently follow up and monitor the progress of the hydro
projects.
# Review meetings are taken by Ministry regularly with the concerned
officers of CEA, equipment manufacturers, State Utilities/CPSUs/ Project
developers, etc.