THE MINISTER OF NEW AND RENEWABLE ENERGY
(DR. FAROOQ ABDULLAH)
(a): Yes, Madam.
(b): The Government has approved implementation of a ââScheme for Setting up of Grid-connected Solar
PV Power Projects of 750 MW aggregate capacity on Build-Own-Operate basis under batch-1 of 2nd
phase of the National Solar Mission (NSM) with Viability Gap Funding (VGF) support to the tune of
Rs.1875crore (maximum) from the National Clean Energy Fund (NCEF)ââ on 3rd October 2013.
The scheme envisages setting up of the projects on Build-Own-Operate basis, purchase of the generated
power by Solar Energy Corporation of India (SECI) at a fixed levelised tariff of Rs.5.45 per kWh for 25 years
and its onward sale to willing State Utilities/ Discoms at a fixed tariff of Rs.5.50 per unit for 25 years. The
projects will be selected based on a process of reverse bidding on VGF required by the developers. Detailed
guidelines for implementation of the scheme have been issued by the Ministry on 25.10.2013 and Request for
Selection (RfS) document has been issued by SECI on 28.10.2013. The closing date for receipt of proposals
in response to the RfS is 28.12.2013.