THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)
(a) to (c) The details such as project features, physical progress, delay due to COVID and completion date of 2 bypasses at Vijayawada are as under:
Description Bypass –I Bypass-II
Package name From Chinna Avutupalli to Gollapudi (Package-III) From Gollapudi to Chinnakakani (Package-IV)
Lane Configuration 6-lane 6-lane
Length 30 km 17.88 km
Awarded bid project cost (Rs. in crore) 1148.4 1546.31
Date of start 18.02.2021 07.07.2021
Name of Concessionaire M/s Megha Engineering India Ltd. M/s Vijaywada Bypass Project Private Limited.
Physical progress 23.00% 3.36%
Delay due to COVID Due to impact of second wave COVID-19, the progress of work got delayed. As such the Concessionaire could not achieve the scheduled Project Milestone-I due on 17.07.2021, however, the same was achieved on 13.10.2021. There is no delay on account of COVID-19. However, there is delay owing to consistent rains since 2-3 months in the project area.
Scheduled date of completion 17.02.2023 04.01.2024
*****