THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL AND NEW & RENEWABLE ENERGY ( SHRI PIYUSH GOYAL )
(a) : Yes, Madam. Two public sector hydro power projects in the central sector are presently under Survey and Investigation in the North Eastern Region (NER) of the country.
(b) : The details of these projects are given below:
Sl.No. Name of Project District /River State Installed Target date of Implementing Agency Capacity preparation of (MW) DPR 1. Siang Upper stage-IINEEPCO Upper Siang/Siang Arunachal 3750 January,2016 2. Mawphu Hydro Electric East Khasi Hills/Umiew Pradesh 75 March, 2015 Project stage-II NEEPCO Meghalaya
NEEPCO has an approved outlay of Rs. 80.87 crore for Survey & Investigation for the year 2014-15.
(c) to (e) : Both the above referred projects have obtained the Terms of Reference (ToR) from Ministry of Environment & Forests and Climate Change (MoEF&CC) and have commenced the Environment Impact Assessment (EIA)/Environmental Management Plan (EMP) studies.