THE MINISTER OF STATE IN THE DEPARTMENT OF ATOMIC ENERGY
(SMT. VASUNDHARA RAJE)
(a) to (d) The original scheduled date of criticality for the
Rajasthan Atomic Power Project Units 3&4 (RAPP-3&4)
were May 1995 and November 1995 respectively. The
completion of the Project got delayed mainly due to
the `hold` put by the Atomic Energy Regulatory Board
(AERB) on the civil construction work of RAPP 3&4
consequent on the delamination incident of Unit-1
of the Kaiga Atomic Power Project in May 1994. There
has been a cost over-run of Rs.404 crore over the latest
approved estimate of Rs.2107 crore due to change in scope
of work, escalation, taxes & duties, foreign exchange
variation, increase in Interest During Construction (IDC)
etc. resulting from the time overrun. Unit-3 has now been
completed and synchronised to the grid on 10.3.2000. The
expected date of criticality of Unit-4 is November, 2000.