(a) whether the Government has any plans to implement
Sagarmala project in Karnataka;
(b) if so, the details thereof; and
(c) the proposal/plan of the Government to protect the
livelihood of the people affected by this project?
(a) whether the Government has any plans to implement
Sagarmala project in Karnataka;
(b) if so, the details thereof; and
(c) the proposal/plan of the Government to protect the
livelihood of the people affected by this project?
(a) & (b) 31 Projects have been identified under Sagarmala Programme in the state of Karnataka for enhancing the infrastructure related to Port Modernisation, Port Connectivity enhancement and Coastal Community Development. These projects are being implemented by Central Ministries, IWAI, Indian Railways, NHAI, State Government and Major Port. The details of projects in Karnataka undertaken under Sagarmala Programme is annexed.
(c) As a part of the project development, the respective project proponents are required to prepare the Social and Environment Impact Assessment Report to ensure due diligence has been done by them to assess the potential impact of the proposed project on the community and environment. Simultaneously, they need to prepare and implement Social and Environmental Management Plan to mitigate the negative impacts which was investigated during the studies of baseline conditions, impact assessment and evaluation for the project. Further, Improvement in livelihood of communities in coastal area is also undertaken through implementation of projects identified under coastal community development pillar of Sagarmala.
Annex
List of projects in Karnataka
<pre>
S.No. Project Name Project Category Stage Project Cost(in cr.)
1 4 Laning of ShiradiGhat Road- Concretizing for smoothening of traffic road. Road Under Implementation 1200
2 2 to 4 laning of NH-169 from Mangalore to Mudabidri to Karkala Road Submit Proposal 1067
3 SH-2 Haveri-Yekambi-SH-69 Yekambi-Kumta-Belekerizx Road Under Implementation 1451
4 2 to 4 laning of NH-206 Tumakuru -Honnavar Port Road Under Implementation 500
5 Upgradation of platform no. 2 and 3 in the Port Marshalling Yard at NMPT Rail Project Completed 5
6 Upgradation of Railway line 1 and 2 at NMPT Rail Project Completed 5
7 Rail Connectivty to Belekeri Port Rail Submit Proposal 400
8 Third stage expansion including modernisation of the existing fishing harbour of Malpe in Udupi District in Karnataka Fisheries Project Completed 50
9 Modernisation of the existing fishing harbour at Amadalli in Uttara Kannada Fisheries Project Completed 19
10 Coastal Districts Skill Development Program - Phase I -Karnataka Skill Development Project Completed 2
11 Development of Fishing Harbour at Kulai Fisheries Under Tendering 197
12 By Pass road from NH to Belekeri Port and Rail connectivity from harwada to Belekeri Road DPR Preparation 75
13 Road connectivity from kasarkad side of Honnavar Port to NH Road DPR Preparation 50
14 Develop NW43 -l0 km from
Confluence of Netravathi river to
Mangalore Port Bridge on Gurupur river Inland Waterways DPR Preparation 100
15 Develop NW74 -78 km from
Arabian Sea at Bengre to Netravathi Dam- Dharmsthala on Netravathi river Inland Waterways DPR Preparation 500
16 Develop NW51 -23 km from Kabini Dam to Beeramballi on Kabini river Inland Waterways DPR Preparation 200
17 Development of HejmaadiKodi Fishing Harbour in Udupi District Fisheries DPR Preparation 139
18 Coastal Districts Skill Development Program - Phase 2 -Karnataka Skill Development Submit Proposal 6
19 Netravati-Mangalore Rail Under Implementation 28
20 Kankanadi-Panambur Patch doubling Rail Under Implementation 238
21 Construction of berth18 in western dock Arm at NMPT Port Capacity Addition Project Completed 94
22 Implementation of RFID - NMPT Port Modernization Project Completed 5
23 Development of 30 acres of stack yard and ancillary roads for parking of Ro-Ro cargoes and cars - NMPT Port Modernization Project Completed 22
24 Implementation of Mobile X-Ray Container Scanner at NMPT Port Modernization Project Completed 40
25 Mechanization of Berth 14 and Backup area for handling Container Terminal at NMPT Port Capacity Addition Under Implementation 258
26 Mechanisation of Berth 18 - now 16 for handling bulk cargo at NMPT Port Capacity Addition Project Completed 469
27 Extension of Southern breakwater by 145m and construction of 1-160 m northern break-water at Karwar Port Port Capacity Addition Under Implementation 215
28 Construction of coastal cargo berth at Old Mangaluru Port Port Capacity Addition Submit Proposal 65
29 Construction of Coastal cargo berth of 250 m at Karwar Port Port Capacity Addition Submit Proposal 61
30 Construction of 1258m Wharf at Karwar Port Port Capacity Addition Under Implementation 250
31 Capital Dredging at Old Mangaluru Port -Bengre Side Port Capacity Addition Submit Proposal 29