(a) the progress so far made in construction of Abohar-Fazilka
rail line project;
(b) the expenditure incurred on the project, till date; and
(c) the time by which work on the project is likely to be
completed ?
(a) the progress so far made in construction of Abohar-Fazilka
rail line project;
(b) the expenditure incurred on the project, till date; and
(c) the time by which work on the project is likely to be
completed ?
MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI R.VELU )
(a): Final location survey has been completed. Soil investigation
for major bridges completed. Land acquisition is under process and an
amount of Rs.6.20 crore has been deposited with the State Government
of Punjab for acquisition of land.
(b): An expenditure of about Rs. 6.47 crore (provisional) has been
incurred on the project upto end of Feb. â05.
(c): The target date for completion of this project has not yet
been fixed.