(a) whether the work of doubling the railway track from Gorakhpur to Sahajnava of North Eastern Railway has been sanctioned; and
(b) if so, the time by which this scheme is likely to be completed?
(a) whether the work of doubling the railway track from Gorakhpur to Sahajnava of North Eastern Railway has been sanctioned; and
(b) if so, the time by which this scheme is likely to be completed?
MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI R. VELU)
(a): Yes, Sir.
(b): Gorakhpur-Domingarh (5.63 kms) section has been completed. Target for completion of remaining section has not been fixed so far.