THE MINISTER OF STATE IN THE MINISTRY OF POWER
( SHRIMATI JAYAWANTI MEHTA )
(a) : Hydro capacity installation of 9282.2 MW was programmed
to be added during 8th Plan which was revised to 3796.70 MW after
the mid term appraisal. Hydro capacity installation of 2427.65 MW
was actually achieved during the 8th Plan period.
(b) : Slippage in the addition of planned hydro capacity during
8th Plan was mainly due to problems relating to Resettlement and
Rehabilitation, law and order, funds constraints, contractor
problems, slow progress of works, delay in award of works, natural
calamities, inter-state disputes and low priority given by some
State Governments.
(c) : As on 29.2.2000, 29 hydro projects, 5 in
private sector and 24 in public sector, excluding those which have
got investment sanction have been accorded techno-economic
clearance by Central Electricity Authority (CEA).
(d) & (e) : A re-assessment of hydro electric potential of
the country carried out during 1978-87 have indicated hydro
electric potential of 84044 MW (at 60% load factor) of major/medium
schemes. As on 1.2.2000, out of this assessed potential, hydro
electric projects of potential of 16.13% have been developed, 6.25%
are under construction and 3.34% have been cleared by the Central
Electricity Authority. Therefore, 74.28% of the hydro electric
potential of the country is yet to be harnessed. The reasons for
slow development of hydro electric potential are problems relating
to rehabilitation, availability of good contractors, environment
and forest clearance, law and order, land acquisition, geological
surprises, apart from inter state aspects and slow development of
North Eastern Region.
(f) & (g) : The Planning Commission had formulated a
capacity addition programme of 40245.2 MW from/during 9th Plan,
Sector-wise details are given below:
MW Central 11909.0 State 10747.7 Private 17588.5
State-wise details of the programme are at
Annex-1. This does not include liquid fuel capacity of 6000 MW for
which State-wise projects have not yet been identified. Mid term
appraisal carried out in July, 1999 has indicated 28097.2 MW
feasible capacity addition.