Question : ELECTRIFICATION OF RAILWAY LINES



(a) whether the Railways have accorded approval for electrification of certain rail lines in the country including Madhya Pradesh during the last three years;

(b) if so, the total length of railway lines for which approval has been accorded;

(c) whether electrification of Indore-Ujjain railway line has also been approved; and

(d) if so, the time by when electrification work on these lines is likely to be started?

Answer given by the minister


MINISTER OF STATE IN THE MINISTRY OF RAILWAYS(SHRI K.H.MUNIYAPPA)

(a): Yes,Madam.During last three years from 2006-07 to 2008-09, certain rail lines are approved for electrification. The details are given in Appendix.

(b): The total length of railway lines approved for electrification is as follows:-


Year Route Kilometres

2006-07 1180

2007-08 1165

2008-09 1944

Total 4289

(c) & (d): Yes, Madam. Electrification work is in progress on Indore-Ujjain rail line and targeted for completion by March 2010.