THE MINISTER OF STATE FOR MINES & MINERALS
(SMT. RITA VERMA)
(a) to (c) The details of potable water supply schemes
indicating number of projects approved, completed and
pending for completion alongwith sanctioned amount in
respect of each subsidiary company of Coal India Limited
including Central Coalfields Limited and Bharat Coking Coal
Limited during the last 3 years i.e. 1997-98, 1998-99 and
1999-2000 are given as under :
Company Number of Number of Number of Amount projects projects projects sanctioned approved completed pending/un (Rs. in der lakhs) completion
ECL 3 - 3 888.00
BCCL 1 1 - 17.42
CCL 1 - 1 63.33
WCL 19 12 7 1015.20
NCL No new water treatment plant or expansions were done since last 3 years. However, new conveyance line extended from the existing treatment plant to feed Jhingurdah, Singrauli and Kakri Project at a cost of Rs.5.16 crores.
SECL 2 - 2 302.82
MCL 1 1 - 43.73
CMPDIL - - - -